Assessment Year | 2015 |
---|---|
Principal Product | Hardwood flooring |
NAICS | 321918: Other Millwork (including Flooring) |
SIC | 2426: Hardwood Dimension and Flooring Mills |
Sales Range | $50 M to 100M |
# of Employees | 175 |
Plant Area |
100,000
ft2
|
Annual Production | 2,000
thousand feet
|
Production Hrs. Annual | 5,000
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $699,120 | 10,825,500 |
kWh
|
$0.065 |
Electricity Demand | $308,879 | 33,896 |
kW-mo/yr
|
$9.11 |
Wood | $1 | 136,672 |
MMBtu
|
$0.000 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $92,694 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $48,542 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $32,534 | $30,000 |
$32,534
500,525
kWh
|
- | - | - | - | - | |
02 | 2.1213: Direct warmest air to combustion intake | $4,151 | $2,000 | - | - |
$4,151
-
MMBtu
|
- | - | - | |
03 | 2.2136: Install / repair insulation on steam lines | $7,703 | $4,873 | - | - |
$7,703
-
MMBtu
|
- | - | - | |
04 | 2.2121: Increase amount of condensate returned | $5,565 | $2,400 | - | - |
$1,605
-
MMBtu
|
$3,960
-
Tgal
|
- | - | |
05 | 2.4226: Use / purchase optimum sized compressor | $11,473 | $16,125 |
$11,473
176,504
kWh
|
- | - | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,106 | $100 |
$1,062
16,337
kWh
|
$204
-
kW-mo/yr
|
- | - | $(-100.0) | $(-60.0) | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,690 | $100 |
$1,418
21,812
kWh
|
$272
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $1,072 | $3,600 |
$582
8,953
kWh
|
$490
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,889 | $30,733 |
$5,674
87,288
kWh
|
$3,132
-
kW-mo/yr
|
- | - | - | $83 | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $468 | $278 |
$222
3,410
kWh
|
$186
-
kW-mo/yr
|
- | - | - | $60 | |
11 | 2.7135: Install occupancy sensors | $261 | $497 |
$261
4,016
kWh
|
- | - | - | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $189 | $48 |
$83
1,282
kWh
|
$16
-
kW-mo/yr
|
- | - | - | $90 | |
13 | 2.7134: Use photocell controls | $1,636 | $700 |
$1,636
25,167
kWh
|
- | - | - | - | - | |
14 | 2.5123: Reduce fluid flow rates | $8,008 | $11,000 |
$4,350
66,931
kWh
|
$3,658
-
kW-mo/yr
|
- | - | - | - | |
15 | 2.7313: Recycle air for heating, ventilation and air conditioning | $5,331 | $14,100 | - | - |
$5,331
-
MMBtu
|
- | - | - | |
16 | 2.7224: Reduce space conditioning during non-working hours | $192 | $221 |
$192
2,960
kWh
|
- | - | - | - | - | |
17 | 2.2437: Recover waste heat from equipment | $218 | $100 | - | - |
$218
-
MMBtu
|
- | - | - | |
18 | 2.4151: Develop a repair/replace policy | $1,205 | $4,256 |
$655
10,074
kWh
|
$550
-
kW-mo/yr
|
- | - | - | - | |
19 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,003 | $93 |
$545
8,385
kWh
|
$458
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $92,694 | $121,224 |
$60,687
933,644
kWh
|
$8,966
-
kW-mo/yr
|
$19,008
-
MMBtu
|
$3,960
-
Tgal
|
$(-100.0) | $173 | ||
TOTAL IMPLEMENTED | $48,542 | $67,415 |
$40,230
618,916
kWh
|
$4,088
-
kW-mo/yr
|
$4,151
-
MMBtu
|
- | $(-100.0) | $173 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs