Assessment Year | 2014 |
---|---|
Principal Product | Napkins and towels |
NAICS | 322291: Sanitary Paper Product Manufacturing |
SIC | 2676: Sanitary Paper Products |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
250,000
ft2
|
Annual Production | 140,000,000
lb
|
Production Hrs. Annual | 8,600
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,135,951 | 67,526,297 |
kWh
|
$0.032 |
Electricity Demand | $1,775,365 | 112,494 |
kW-mo/yr
|
$15.78 |
Electricity Fees | $105,184 | - |
|
- |
Natural Gas | $65,573 | 10,483 |
MMBtu
|
$6.26 |
Other Energy | $1,574,576 | 198,319 |
MMBtu
|
$7.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $498,375 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $403,599 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4323: Use optimum size and capacity equipment | $207,427 | $102,000 |
$122,253
3,868,761
kWh
|
$85,174
-
kW-mo/yr
|
- | - | - | |
02 | 2.2113: Repair or replace steam traps | $75,916 | $5,100 | - | - |
$78,733
-
MMBtu
|
$(-417.0) | $(-2,400.0) | |
03 | 2.2444: Use hot process fluids to preheat incoming process fluids | $104,811 | $52,500 | - | - |
$104,811
-
MMBtu
|
- | - | |
04 | 2.2135: Repair and eliminate steam leaks | $21,819 | $2,200 | - | - |
$23,619
-
MMBtu
|
$(-1,200.0) | $(-600.0) | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $67,692 | $258,028 |
$37,258
1,179,060
kWh
|
$25,962
-
kW-mo/yr
|
- | - | $4,472 | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,850 | $500 |
$1,703
53,891
kWh
|
$1,187
-
kW-mo/yr
|
- | $(-800.0) | $(-240.0) | |
07 | 2.4239: Eliminate or reduce compressed air usage | $4,436 | $10,000 |
$2,614
82,732
kWh
|
$1,822
-
kW-mo/yr
|
- | - | - | |
08 | 2.4226: Use / purchase optimum sized compressor | $7,811 | $17,150 |
$4,604
145,704
kWh
|
$3,207
-
kW-mo/yr
|
- | - | - | |
09 | 2.4235: Remove or close off unneeded compressed air lines | $2,308 | $2,500 |
$1,361
43,074
kWh
|
$947
-
kW-mo/yr
|
- | - | - | |
10 | 2.4151: Develop a repair/replace policy | $2,323 | $4,256 |
$1,369
43,317
kWh
|
$954
-
kW-mo/yr
|
- | - | - | |
11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $664 | $72 |
$392
12,391
kWh
|
$272
-
kW-mo/yr
|
- | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $526 | $160 |
$135
4,275
kWh
|
$92
-
kW-mo/yr
|
- | - | $299 | |
13 | 2.7135: Install occupancy sensors | $792 | $2,118 |
$792
25,049
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $498,375 | $456,584 |
$172,481
5,458,254
kWh
|
$119,617
-
kW-mo/yr
|
$207,163
-
MMBtu
|
$(-2,417.0) | $1,531 | ||
TOTAL IMPLEMENTED | $403,599 | $415,228 |
$161,214
5,101,712
kWh
|
$112,323
-
kW-mo/yr
|
$128,430
-
MMBtu
|
$(-2,000.0) | $3,632 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs