| Assessment Year | 2005 |
|---|---|
| Principal Product | Spices |
| NAICS | 311942: Spice and Extract Manufacturing |
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 65 |
| Plant Area |
94,500
ft2
|
| Annual Production | 8,722
ton
|
| Production Hrs. Annual | 4,992
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $123,892 | 1,486,420 |
kWh
|
$0.083 |
| Electricity Demand | $54,917 | 6,910 |
kW-mo/yr
|
$7.95 |
| Natural Gas | $39,513 | 6,745 |
MMBtu
|
$5.86 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,497 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,847 | $1,200 |
$5,397
65,022
kWh
|
$1,450
-
kW-mo/yr
|
|
| 02 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $3,467 | $4,000 |
$3,467
41,775
kWh
|
- | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,748 | $2,000 | - |
$2,748
-
kW-mo/yr
|
|
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,613 | $320 |
$1,613
19,438
kWh
|
- | |
| 05 | 2.4314: Use synthetic lubricant | $429 | $200 |
$342
4,123
kWh
|
$87
-
kW-mo/yr
|
|
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $2,078 | $110 |
$1,587
14,166
kWh
|
$491
-
kW-mo/yr
|
|
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,315 | $40,077 |
$7,870
94,814
kWh
|
$2,445
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $27,497 | $47,907 |
$20,276
239,338
kWh
|
$7,221
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs