Assessment Year | 1989 |
---|---|
Principal Product | STEEL CASING AND TUBING |
NAICS |
n/a
|
SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 69 |
Plant Area |
n/a
|
Annual Production | 6,600
ton
|
Production Hrs. Annual | 4,144
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $301,358 | 6,276,671 |
kWh
|
$0.048 |
Natural Gas | $562,325 | 178,887 |
MMBtu
|
$3.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $86,170 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $69,580 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.8113: Purchase gas directly from a contract gas supplier | $59,200 | - | - |
$59,200
-
MMBtu
|
|
02 | 2.2414: Use waste heat from hot flue gases to preheat | $11,080 | $24,686 |
$(-870.0)
(-13,482)
kWh
|
$11,950
-
MMBtu
|
|
03 | 2.2514: Cover open tanks | $9,300 | - | - |
$9,300
-
MMBtu
|
|
04 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $2,440 | $900 |
$2,440
36,635
kWh
|
- | |
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,320 | - | - |
$1,320
-
MMBtu
|
|
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,210 | $940 |
$1,210
38,101
kWh
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $540 | $420 |
$540
17,585
kWh
|
- | |
08 | 2.2511: Insulate bare equipment | $1,080 | $1,080 | - |
$1,080
-
MMBtu
|
|
TOTAL RECOMMENDED | $86,170 | $28,026 |
$3,320
78,839
kWh
|
$82,850
-
MMBtu
|
||
TOTAL IMPLEMENTED | $69,580 | $1,080 | - |
$69,580
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs