ITAC Assessment: NC0513
ITAC logo
ITAC Assessment: NC0513
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Wool yarn and fabric
NAICS 313210: Broadwoven Fabric Mills
SIC 2231: Broadwoven Fabric Mills, Wool (Including Dyeing and Finishing)
Sales Range $10
M
to 50
M
# of Employees 450
Plant Area 647,000
ft2
Annual Production 9,000,000
lb
Production Hrs. Annual 4,800
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,431,745 32,044,344
kWh
Electricity Demand $1,005,509 89,199
kW-mo/yr
Natural Gas $1,055,091 202,600
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $456,571 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $368,430

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4151: Develop a repair/replace policy $137,290 $454,945 $84,211
1,883,905
kWh
$53,079
-
kW-mo/yr
- - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $89,082 $860 $54,641
1,222,397
kWh
$34,441
-
kW-mo/yr
- - -
03 2.4224: Upgrade controls on compressors $21,458 $10,000 $10,639
238,007
kWh
$10,819
-
kW-mo/yr
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,428 $100 $4,642
103,843
kWh
$2,926
-
kW-mo/yr
- $(-900.0) $(-240.0)
05 2.4239: Eliminate or reduce compressed air usage $325 $175 $325
7,281
kWh
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $34,462 $24,205 $21,138
472,896
kWh
$13,324
-
kW-mo/yr
- - -
07 2.7111: Reduce illumination to minimum necessary levels $1,117 $325 $611
13,680
kWh
$386
-
kW-mo/yr
- - $120
08 2.7135: Install occupancy sensors $3,462 $3,470 $3,462
77,488
kWh
- - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $835 $240 $287
6,413
kWh
$99
-
kW-mo/yr
- - $449
10 2.7134: Use photocell controls $47 $80 $47
1,056
kWh
- - - -
11 2.1232: Keep boiler tubes clean $48,265 $15,000 - - $48,265
-
MMBtu
- -
12 2.2113: Repair or replace steam traps $40,007 $6,200 - - $52,777
-
MMBtu
$(-1,250.0) $(-11,520.0)
13 2.2135: Repair and eliminate steam leaks $20,840 $20,000 - - $20,840
-
MMBtu
- -
14 2.2121: Increase amount of condensate returned $9,159 $5,600 - - $9,159
-
MMBtu
- -
15 2.1232: Keep boiler tubes clean $13,546 $500 - - $13,546
-
MMBtu
- -
16 2.2123: Insulate feedwater tank $438 $257 - - $438
-
MMBtu
- -
17 2.2136: Install / repair insulation on steam lines $20,435 $19,607 - - $20,435
-
MMBtu
- -
18 2.2437: Recover waste heat from equipment $9,375 $37,264 - - $9,375
-
MMBtu
- -
TOTAL RECOMMENDED $456,571 $598,828 $180,003
4,026,966
kWh
$115,074
-
kW-mo/yr
$174,835
-
MMBtu
$(-2,150.0) $(-11,191.0)
TOTAL IMPLEMENTED $368,430 $511,247 $158,207
3,539,334
kWh
$101,364
-
kW-mo/yr
$122,320
-
MMBtu
$(-2,150.0) $(-11,311.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs