ITAC Assessment: NC0510
ITAC logo
ITAC Assessment: NC0510
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Non-woven filtering
NAICS 313230: Nonwoven Fabric Mills
SIC 2299: Textile goods, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 160,000
ft2
Annual Production 9,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $420,798 11,026,300
kWh
Electricity Demand $432,765 26,245
kW-mo/yr
Electricity Fees $9,051 -
LPG $109,783 5,890
MMBtu
Fuel Oil #2 $639,293 27,394
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $152,306 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $92,104

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $55,430 $1,200 - - $55,430
-
MMBtu
- - -
02 2.2121: Increase amount of condensate returned $5,472 $4,800 - - $5,472
-
MMBtu
- - -
03 2.2124: Install de-aerator in place of condensate tank $1,500 $1,000 - - - - $1,500 -
04 2.2437: Recover waste heat from equipment $39,042 $3,000 - - $39,042
-
MMBtu
- - -
05 2.2113: Repair or replace steam traps $26,718 $67,500 - - $31,976
-
MMBtu
$(-938.0) - $(-4,320.0)
06 2.2437: Recover waste heat from equipment $9,896 $1,750 - - $9,896
-
MMBtu
- - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,422 $100 $2,914
78,330
kWh
$1,888
-
kW-mo/yr
- $(-300.0) - $(-80.0)
08 2.7135: Install occupancy sensors $1,444 $2,082 $1,444
38,808
kWh
- - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $943 $1,993 $595
16,000
kWh
$385
-
kW-mo/yr
- - - $(-37.0)
10 2.7142: Utilize higher efficiency lamps and/or ballasts $811 $3,523 $492
13,230
kWh
$319
-
kW-mo/yr
- - - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $836 $240 $239
6,413
kWh
$148
-
kW-mo/yr
- - - $449
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $533 $286 $286
7,686
kWh
$247
-
kW-mo/yr
- - - -
13 2.4151: Develop a repair/replace policy $2,594 $4,256 $1,574
42,310
kWh
$1,020
-
kW-mo/yr
- - - -
14 2.2612: Use cooling tower water instead of refrigeration $2,665 $8,500 $1,617
43,470
kWh
$1,048
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $152,306 $100,230 $9,161
246,247
kWh
$5,055
-
kW-mo/yr
$141,816
-
MMBtu
$(-1,238.0) $1,500 $(-3,988.0)
TOTAL IMPLEMENTED $92,104 $77,638 $5,684
152,781
kWh
$2,740
-
kW-mo/yr
$87,406
-
MMBtu
$(-1,238.0) $1,500 $(-3,988.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs