Assessment Year | 2012 |
---|---|
Principal Product | Carpeting |
NAICS | 314110: Carpet and Rug Mills |
SIC | 2273: Carpets and Rugs |
Sales Range | $100 M to 500M |
# of Employees | 375 |
Plant Area |
530,000
ft2
|
Annual Production | 60,000
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,198,695 | 19,370,580 |
kWh
|
$0.062 |
Electricity Demand | $220,784 | 38,423 |
kW-mo/yr
|
$5.75 |
Natural Gas | $423,234 | 72,955 |
MMBtu
|
$5.80 |
Coal | $1,878,818 | 397,623 |
MMBtu
|
$4.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $329,689 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,898 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Coal Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $146,006 | $260,000 |
$146,391
2,364,960
kWh
|
$26,151
-
kW-mo/yr
|
$(-26,536.0)
-
MMBtu
|
- | - | - | |
02 | 2.2113: Repair or replace steam traps | $29,233 | $9,100 | - | - |
$39,643
-
MMBtu
|
- | $(-1,660.0) | $(-8,750.0) | |
03 | 2.2135: Repair and eliminate steam leaks | $3,142 | $2,100 | - | - |
$3,052
-
MMBtu
|
$90
-
Tgal
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $43,177 | $98,248 |
$36,187
584,776
kWh
|
$6,466
-
kW-mo/yr
|
- | - | - | $524 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,871 | $80,231 |
$21,080
340,646
kWh
|
$3,791
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,787 | $6,902 |
$4,286
69,264
kWh
|
$766
-
kW-mo/yr
|
- | - | - | $735 | |
07 | 2.7135: Install occupancy sensors | $42,119 | $4,405 |
$42,119
680,639
kWh
|
- | - | - | - | - | |
08 | 2.4226: Use / purchase optimum sized compressor | $16,624 | - |
$16,624
268,560
kWh
|
- | - | - | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,756 | $500 |
$10,110
163,374
kWh
|
$1,286
-
kW-mo/yr
|
- | - | $(-2,400.0) | $(-240.0) | |
10 | 2.4221: Install compressor air intakes in coolest locations | $2,532 | $3,200 |
$2,148
34,719
kWh
|
$384
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.4151: Develop a repair/replace policy | $6,426 | $7,515 |
$5,452
88,106
kWh
|
$974
-
kW-mo/yr
|
- | - | - | - | |
12 | 2.2136: Install / repair insulation on steam lines | $897 | $1,290 | - | - |
$897
-
MMBtu
|
- | - | - | |
13 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $119 | $11 |
$101
1,630
kWh
|
$18
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $329,689 | $473,502 |
$284,498
4,596,674
kWh
|
$39,836
-
kW-mo/yr
|
$17,056
-
MMBtu
|
$90
-
Tgal
|
$(-4,060.0) | $(-7,731.0) | ||
TOTAL IMPLEMENTED | $11,898 | $2,600 |
$10,110
163,374
kWh
|
$1,286
-
kW-mo/yr
|
$3,052
-
MMBtu
|
$90
-
Tgal
|
$(-2,400.0) | $(-240.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Coal Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs