ITAC Assessment: NC0429
ITAC logo
ITAC Assessment: NC0429
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Heavy duty transmissions
NAICS 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 400
Plant Area 250,000
ft2
Annual Production 10,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $785,136 22,540,800
kWh
Electricity Demand $369,317 40,632
kW-mo/yr
Electricity Fees $3,387 -
Natural Gas $298,189 48,537
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $55,947 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,733

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4226: Use / purchase optimum sized compressor $27,312 - $19,895
570,200
kWh
$7,417
-
kW-mo/yr
- -
02 2.4226: Use / purchase optimum sized compressor $21,573 $45,000 $6,255
179,588
kWh
$15,318
-
kW-mo/yr
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,733 $100 $2,603
74,727
kWh
$970
-
kW-mo/yr
$(-600.0) $(-240.0)
04 2.2437: Recover waste heat from equipment $3,499 $5,803 $3,566
102,391
kWh
$(-67.0)
-
kW-mo/yr
- -
05 2.4151: Develop a repair/replace policy $830 $2,077 $478
13,710
kWh
$352
-
kW-mo/yr
- -
TOTAL RECOMMENDED $55,947 $52,980 $32,797
940,616
kWh
$23,990
-
kW-mo/yr
$(-600.0) $(-240.0)
TOTAL IMPLEMENTED $2,733 $100 $2,603
74,727
kWh
$970
-
kW-mo/yr
$(-600.0) $(-240.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs