ITAC Assessment: NC0399
ITAC logo
ITAC Assessment: NC0399
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Rubber molded goods
NAICS 326291: Rubber Product Manufacturing for Mechanical Use
SIC 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 81,800
ft2
Annual Production 17,000,000
units
Production Hrs. Annual 6,000
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $128,280 53,264,000
kWh
Electricity Demand $212,035 14,166
kW-mo/yr
Natural Gas $510,278 49,185
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $98,323 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $51,119

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4226: Use / purchase optimum sized compressor $1,597 $100 $1,597
41,485
kWh
- - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $330 $200 $445
11,548
kWh
$305
-
kW-mo/yr
- $(-300.0) $(-120.0)
03 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $40,261 - $(-172.0)
(-4,476)
kWh
$(-119.0)
-
kW-mo/yr
$40,552
-
MMBtu
- -
04 2.2511: Insulate bare equipment $1,429 $5,438 - - $1,429
-
MMBtu
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $17,471 - $10,769
279,720
kWh
$7,418
-
kW-mo/yr
- $(-1,020.0) $304
06 2.4151: Develop a repair/replace policy $7,151 $23,576 $4,233
109,952
kWh
$2,918
-
kW-mo/yr
- - -
07 2.2441: Preheat boiler makeup water with waste process heat $6,943 $8,852 $(-187.0)
(-4,849)
kWh
$(-128.0)
-
kW-mo/yr
$7,258
-
MMBtu
- -
08 2.2136: Install / repair insulation on steam lines $4,744 $1,550 - - $4,744
-
MMBtu
- -
09 2.1233: Analyze flue gas for proper air/fuel ratio $16,805 $6,000 - - $16,805
-
MMBtu
- -
10 2.2511: Insulate bare equipment $1,592 $2,600 $136
3,535
kWh
- $1,456
-
MMBtu
- -
TOTAL RECOMMENDED $98,323 $48,316 $16,821
436,915
kWh
$10,394
-
kW-mo/yr
$72,244
-
MMBtu
$(-1,320.0) $184
TOTAL IMPLEMENTED $51,119 $39,464 $17,180
446,240
kWh
$10,641
-
kW-mo/yr
$24,434
-
MMBtu
$(-1,320.0) $184
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs