Assessment Year | 2006 |
---|---|
Principal Product | Coated paper cartons |
NAICS | 322212: Folding Paperboard Box Manufacturing |
SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
Sales Range | $50 M to 100M |
# of Employees | 131 |
Plant Area |
165,000
ft2
|
Annual Production | 94,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $330,590 | 13,212,761 |
kWh
|
$0.025 |
Electricity Demand | $465,960 | 41,506 |
kW-mo/yr
|
$11.23 |
Electricity Fees | $6,252 | - |
|
- |
Natural Gas | $339,453 | 28,418 |
MMBtu
|
$11.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $95,421 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $53,794 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1133: Adjust burners for efficient operation | $38,892 | $2,000 | - | - |
$38,892
-
MMBtu
|
- | - | |
02 | 2.2135: Repair and eliminate steam leaks | $2,868 | $500 | - | - |
$2,868
-
MMBtu
|
- | - | |
03 | 2.2113: Repair or replace steam traps | $741 | $500 | - | - |
$741
-
MMBtu
|
- | - | |
04 | 2.7313: Recycle air for heating, ventilation and air conditioning | $33,467 | $28,785 | - | - |
$33,467
-
MMBtu
|
- | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $8,141 | $20,000 |
$8,141
207,153
kWh
|
- | - | - | - | |
06 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $2,687 | $1,485 |
$1,885
47,968
kWh
|
$802
-
kW-mo/yr
|
- | - | - | |
07 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $1,249 | $2,000 |
$1,320
33,600
kWh
|
$591
-
kW-mo/yr
|
- | - |
$(-662.0)
-
Tgal
|
|
08 | 2.4151: Develop a repair/replace policy | $2,023 | $1,654 |
$1,422
36,172
kWh
|
$601
-
kW-mo/yr
|
- | - | - | |
09 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,683 | - | - |
$1,683
-
kW-mo/yr
|
- | - | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $753 | $50 |
$528
13,440
kWh
|
$225
-
kW-mo/yr
|
- | - | - | |
11 | 2.7134: Use photocell controls | $376 | $400 |
$376
9,155
kWh
|
- | - | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,209 | $1,803 |
$850
21,641
kWh
|
$359
-
kW-mo/yr
|
- | - | - | |
13 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,332 | $200 |
$1,158
-
kWh
|
$6,174
-
kW-mo/yr
|
- | $(-6,000.0) | - | |
TOTAL RECOMMENDED | $95,421 | $59,377 |
$15,680
369,129
kWh
|
$10,435
-
kW-mo/yr
|
$75,968
-
MMBtu
|
$(-6,000.0) |
$(-662.0)
-
Tgal
|
||
TOTAL IMPLEMENTED | $53,794 | $25,104 |
$10,467
265,920
kWh
|
$826
-
kW-mo/yr
|
$42,501
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs