| Assessment Year | 2003 |
|---|---|
| Principal Product | Velour fabrics for recliners |
| NAICS | 313310: Textile and Fabric Finishing Mills |
| SIC | 2299: Textile goods, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 275 |
| Plant Area |
500,000
ft2
|
| Annual Production | 99,000,000
thousand feet
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $598,291 | 21,956,016 |
kWh
|
$0.027 |
| Electricity Demand | $473,209 | 54,027 |
kW-mo/yr
|
$8.76 |
| Electricity Fees | $30,002 | - |
|
- |
| Natural Gas | $1,622,111 | 303,004 |
MMBtu
|
$5.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $81,368 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,100 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3132: Recharge batteries on during off-peak demand periods | $869 | - | - |
$869
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.2491: Use cooling air which cools hot work pieces for space heating | $6,222 | $9,225 | - | - |
$6,222
-
MMBtu
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,018 | $9,911 |
$3,462
128,229
kWh
|
$1,556
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.7124: Make a practice of turning off lights when not needed | $1,686 | $700 |
$1,043
38,640
kWh
|
$643
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.4226: Use / purchase optimum sized compressor | $3,004 | $12,000 |
$3,004
137,172
kWh
|
- | - | - | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $410 | $100 |
$1,126
41,710
kWh
|
$484
-
kW-mo/yr
|
- | $(-800.0) | $(-400.0) | - | |
| 07 | 3.4115: Recover and reuse cooling water | $64,159 | - |
$(-1,975.0)
(-73,142)
kWh
|
- | - | - | - |
$66,134
-
Tgal
|
|
| TOTAL RECOMMENDED | $81,368 | $31,936 |
$6,660
272,609
kWh
|
$3,552
-
kW-mo/yr
|
$6,222
-
MMBtu
|
$(-800.0) | $(-400.0) |
$66,134
-
Tgal
|
||
| TOTAL IMPLEMENTED | $5,100 | $12,800 |
$5,173
217,522
kWh
|
$1,127
-
kW-mo/yr
|
- | $(-800.0) | $(-400.0) | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs