Assessment Year | 2002 |
---|---|
Principal Product | Woven and knitted elastic webbing |
NAICS |
n/a
|
SIC | 2241: Narrow Fabric and Other Smallware Mills: Cotton, Wool, Silk, and Manmade Fiber |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
100,000
ft2
|
Annual Production | 120,000
thousand feet
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $49,108 | 1,730,438 |
kWh
|
$0.028 |
Electricity Demand | $44,832 | 4,626 |
kW-mo/yr
|
$9.69 |
Electricity Fees | $3,890 | - |
|
- |
Natural Gas | $66,822 | 9,452 |
MMBtu
|
$7.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,288 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,890 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $1,453 | $3,876 | - | - |
$1,453
-
MMBtu
|
- | - | - | - | |
02 | 2.4226: Use / purchase optimum sized compressor | $3,063 | $1,500 |
$1,537
54,121
kWh
|
$1,526
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $236 | $50 |
$118
4,160
kWh
|
$118
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.1221: Replace obsolete burners with more efficient ones | $1,543 | $6,300 | - | - |
$1,543
-
MMBtu
|
- | - | - | - | |
05 | 2.2135: Repair and eliminate steam leaks | $4,291 | $2,500 | - | - |
$3,920
-
MMBtu
|
$186
-
Tgal
|
- | $185 | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $200 | $125 |
$41
1,440
kWh
|
$41
-
kW-mo/yr
|
- | - | $125 | - | $(-7.0) | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $682 | $351 |
$334
11,776
kWh
|
$348
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.4151: Develop a repair/replace policy | $820 | $1,753 |
$400
14,075
kWh
|
$420
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $12,288 | $16,455 |
$2,430
85,572
kWh
|
$2,453
-
kW-mo/yr
|
$6,916
-
MMBtu
|
$186
-
Tgal
|
$125 | $185 | $(-7.0) | ||
TOTAL IMPLEMENTED | $6,890 | $10,603 |
$518
18,235
kWh
|
$538
-
kW-mo/yr
|
$5,463
-
MMBtu
|
$186
-
Tgal
|
- | $185 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs