| Assessment Year | 1991 |
|---|---|
| Principal Product | FASTENERS |
| NAICS |
n/a
|
| SIC | 3452: Bolts, Nuts, Screws, Rivets, and Washers |
| Sales Range | $10 M to 50M |
| # of Employees | 195 |
| Plant Area |
n/a
|
| Annual Production | 1,560,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $189,460 | 2,292,497 |
kWh
|
$0.083 |
| Natural Gas | $20,364 | 3,282 |
MMBtu
|
$6.20 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,125 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $18,125 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,147 | - |
$2,147
25,791
kWh
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,160 | $308 |
$2,160
26,084
kWh
|
- | |
| 03 | 2.8114: Change rate schedules or other changes in utility service | $2,849 | $2,500 | - |
$2,849
-
MMBtu
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $851 | $300 |
$851
10,258
kWh
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,456 | - |
$4,456
53,634
kWh
|
- | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $2,570 | $166 |
$2,570
31,067
kWh
|
- | |
| 07 | 2.2122: Install / repair insulation on condensate lines | $88 | $28 | - |
$88
-
MMBtu
|
|
| 08 | 2.2136: Install / repair insulation on steam lines | $374 | $180 | - |
$374
-
MMBtu
|
|
| 09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $509 | $500 | - |
$509
-
MMBtu
|
|
| 10 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,121 | - |
$3,113
37,515
kWh
|
$(-992.0)
-
MMBtu
|
|
| TOTAL RECOMMENDED | $18,125 | $3,982 |
$15,297
184,349
kWh
|
$2,828
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $18,125 | $3,982 |
$15,297
184,349
kWh
|
$2,828
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs