ITAC Assessment: NC0238
ITAC logo
ITAC Assessment: NC0238
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Dyed package yarn
NAICS
n/a
SIC 2299: Textile goods, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 52
Plant Area 25,000
ft2
Annual Production 9,153,750
lb
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $264,417 9,940,500
kWh
Electricity Demand $182,158 19,337
kW-mo/yr
Natural Gas $408,679 103,060
MMBtu
Fuel Oil #6 $121,050 25,008
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,605,600 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $125,249

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Increase in Production Savings
01 3.4154: Eliminate leaks in water lines and valves $1,890 $2,100 - - - $1,890
-
Tgal
- - - - -
02 2.2135: Repair and eliminate steam leaks $3,389 $5,000 - - $3,158
-
MMBtu
$201
-
Tgal
- - $30 - -
03 2.1233: Analyze flue gas for proper air/fuel ratio $12,980 $26,000 - - $12,980
-
MMBtu
- - - - - -
04 2.1232: Keep boiler tubes clean $11,529 $50,000 $11,529
802,462
kWh
- - - - - - - -
05 2.2124: Install de-aerator in place of condensate tank $100,000 $35,000 - - - - - - - $100,000 -
06 2.2113: Repair or replace steam traps $10,000 $9,340 - - $10,782
-
MMBtu
- $(-168.0) - $(-614.0) - -
07 2.2136: Install / repair insulation on steam lines $1,112 $2,405 - - $1,112
-
MMBtu
- - - - - -
08 2.2511: Insulate bare equipment $15,915 $5,922 - - $15,915
-
MMBtu
- - - - - -
09 2.2511: Insulate bare equipment $14,570 $17,855 - - $14,570
-
MMBtu
- - - - - -
10 2.2121: Increase amount of condensate returned $4,818 $6,000 - - $3,081
-
MMBtu
$1,512
-
Tgal
- - $225 - -
11 2.4151: Develop a repair/replace policy $6,185 $17,736 $3,608
135,626
kWh
$2,577
-
kW-mo/yr
- - - - - - -
12 2.4156: Establish a preventative maintenance program $4,536 $1,500 $2,329
87,570
kWh
$1,179
-
kW-mo/yr
- - - $1,028 - - -
13 2.2437: Recover waste heat from equipment $93,319 $15,000 - - $43,211
-
MMBtu
$50,108
-
Tgal
- - - - -
14 2.4321: Upgrade obsolete equipment $3,325,357 $914,253 $101,293
380,802
kWh
- $317,080
-
MMBtu
- $915,376 - - - $1,991,608
TOTAL RECOMMENDED $3,605,600 $1,108,111 $118,759
1,406,460
kWh
$3,756
-
kW-mo/yr
$421,889
-
MMBtu
$53,711
-
Tgal
$915,208 $1,028 $(-359.0) $100,000 $1,991,608
TOTAL IMPLEMENTED $125,249 $59,081 $5,937
223,196
kWh
$3,756
-
kW-mo/yr
$61,344
-
MMBtu
$53,711
-
Tgal
$(-168.0) $1,028 $(-359.0) - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs