ITAC Assessment: NC0235
ITAC logo
ITAC Assessment: NC0235
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Corrugated board and displays
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $50
M
to 100
M
# of Employees 220
Plant Area 330,000
ft2
Annual Production 1,000,000
thousand feet
Production Hrs. Annual 6,864
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $550,042 10,577,735
kWh
Electricity Demand $156,868 31,374
kW-mo/yr
Electricity Fees $300 -
Natural Gas $356,414 54,535
MMBtu
Fuel Oil #2 $59,864 8,180
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $241,302 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $72,125

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
01 2.4226: Use / purchase optimum sized compressor $17,277 $100 $14,793
284,475
kWh
$2,484
-
kW-mo/yr
- - - -
02 4.651: Install back-up equipment $156,500 $1,000 - - - - $156,500 -
03 2.6212: Turn off equipment during breaks, reduce operating time $12,464 $550 - - $12,003
-
MMBtu
$461
-
Tgal
- -
04 2.1131: Repair faulty insulation in furnaces, boilers, etc $30,410 $1,000 - - - - - $30,410
05 2.4151: Develop a repair/replace policy $23,267 $15,570 $19,907
382,822
kWh
$3,360
-
kW-mo/yr
- - - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,171 $2,434 $1,002
19,276
kWh
$169
-
kW-mo/yr
- - - -
07 3.4115: Recover and reuse cooling water $213 $500 - - - $213
-
Tgal
- -
TOTAL RECOMMENDED $241,302 $21,154 $35,702
686,573
kWh
$6,013
-
kW-mo/yr
$12,003
-
MMBtu
$674
-
Tgal
$156,500 $30,410
TOTAL IMPLEMENTED $72,125 $19,104 $35,702
686,573
kWh
$6,013
-
kW-mo/yr
- - - $30,410
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs