| Assessment Year | 2002 |
|---|---|
| Principal Product | Corrugated board and displays |
| NAICS |
n/a
|
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $50 M to 100M |
| # of Employees | 220 |
| Plant Area |
330,000
ft2
|
| Annual Production | 1,000,000
thousand feet
|
| Production Hrs. Annual | 6,864
hrs
|
| Location (State) | South Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $550,042 | 10,577,735 |
kWh
|
$0.052 |
| Electricity Demand | $156,868 | 31,374 |
kW-mo/yr
|
$5.00 |
| Electricity Fees | $300 | - |
|
- |
| Natural Gas | $356,414 | 54,535 |
MMBtu
|
$6.54 |
| Fuel Oil #2 | $59,864 | 8,180 |
MMBtu
|
$7.32 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $241,302 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $72,125 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $17,277 | $100 |
$14,793
284,475
kWh
|
$2,484
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 4.651: Install back-up equipment | $156,500 | $1,000 | - | - | - | - | $156,500 | - | |
| 03 | 2.6212: Turn off equipment during breaks, reduce operating time | $12,464 | $550 | - | - |
$12,003
-
MMBtu
|
$461
-
Tgal
|
- | - | |
| 04 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $30,410 | $1,000 | - | - | - | - | - | $30,410 | |
| 05 | 2.4151: Develop a repair/replace policy | $23,267 | $15,570 |
$19,907
382,822
kWh
|
$3,360
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,171 | $2,434 |
$1,002
19,276
kWh
|
$169
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 3.4115: Recover and reuse cooling water | $213 | $500 | - | - | - |
$213
-
Tgal
|
- | - | |
| TOTAL RECOMMENDED | $241,302 | $21,154 |
$35,702
686,573
kWh
|
$6,013
-
kW-mo/yr
|
$12,003
-
MMBtu
|
$674
-
Tgal
|
$156,500 | $30,410 | ||
| TOTAL IMPLEMENTED | $72,125 | $19,104 |
$35,702
686,573
kWh
|
$6,013
-
kW-mo/yr
|
- | - | - | $30,410 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs