Assessment Year | 2000 |
---|---|
Principal Product | Dyed fabric |
NAICS |
n/a
|
SIC | 2269: Finishers of Textiles, Not elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 111 |
Plant Area |
140,000
ft2
|
Annual Production | 4,500,000
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $113,937 | 3,713,365 |
kWh
|
$0.031 |
Electricity Demand | $79,384 | 9,518 |
kW-mo/yr
|
$8.34 |
Electricity Fees | $6,149 | - |
|
- |
Natural Gas | $495,897 | 116,905 |
MMBtu
|
$4.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $48,247 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,486 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1133: Adjust burners for efficient operation | $4,201 | $2,350 | - | - |
$4,201
-
MMBtu
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,133 | $257 |
$734
23,740
kWh
|
$399
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7122: Disconnect ballasts | $2,900 | $6,800 |
$1,879
61,254
kWh
|
$1,021
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4154: Avoid rewinding motors more than twice | $1,634 | $1,282 |
$1,058
34,583
kWh
|
$576
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,960 | $730 |
$1,154
37,515
kWh
|
$806
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $1,422 | $1,100 |
$810
26,377
kWh
|
$772
-
kW-mo/yr
|
- | - | - | $(-160.0) | |
07 | 2.6231: Utilize controls to operate equipment only when needed | $4,074 | $1,000 | - | - |
$4,074
-
MMBtu
|
- | $(-15,000.0) | $15,000 | |
08 | 2.2444: Use hot process fluids to preheat incoming process fluids | $27,524 | $15,000 | - | - |
$27,524
-
MMBtu
|
- | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $421 | $90 |
$315
10,258
kWh
|
$106
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.2437: Recover waste heat from equipment | $2,603 | $3,000 |
$2,603
205,744
kWh
|
- | - | - | - | - | |
11 | 3.5313: Increase amount of waste recovered for resale | $375 | $500 | - | - | - |
$375
-
lb
|
- | - | |
TOTAL RECOMMENDED | $48,247 | $32,109 |
$8,553
399,471
kWh
|
$3,680
-
kW-mo/yr
|
$35,799
-
MMBtu
|
$375
-
lb
|
$(-15,000.0) | $14,840 | ||
TOTAL IMPLEMENTED | $16,486 | $12,827 |
$4,892
159,144
kWh
|
$3,104
-
kW-mo/yr
|
$8,275
-
MMBtu
|
$375
-
lb
|
$(-15,000.0) | $14,840 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs