| Assessment Year | 2023 |
|---|---|
| Principal Product | Water treatment |
| NAICS | 221310: Water Supply and Irrigation Systems |
| SIC | 4941: Water Supply |
| Sales Range | $50 M to 100M |
| # of Employees | 20 |
| Plant Area |
950,000
ft2
|
| Annual Production | 12,636,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,230,259 | 15,969,400 |
kWh
|
$0.077 |
| Natural Gas | $235,769 | 34,356 |
MMBtu
|
$6.86 |
| TOTAL YEARLY COSTS | $1,466,028 | |||
| RECOMMENDED SAVINGS* | $6,488 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $540 | - |
$540
7,008
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $1,592 | $1,946 |
$1,592
20,674
kWh
|
- | |
| 03 | 2.7231: Use radiant heater for spot heating | $4,356 | $5,979 | - |
$4,356
-
MMBtu
|
|
| TOTAL RECOMMENDED | $6,488 | $7,925 |
$2,132
27,682
kWh
|
$4,356
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs