Assessment Year | 2000 |
---|---|
Principal Product | Flexographic prints |
NAICS |
n/a
|
SIC | 2673: Plastics, Foil, and Coated Paper Bags |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
160,000
ft2
|
Annual Production | 165,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $193,885 | 7,351,407 |
kWh
|
$0.026 |
Electricity Demand | $150,642 | 15,791 |
kW-mo/yr
|
$9.54 |
Electricity Fees | $11,411 | - |
|
- |
Natural Gas | $56,558 | 9,019 |
MMBtu
|
$6.27 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $140,207 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $99,810 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $29,525 | $15,500 |
$(-641.0)
(-24,619)
kWh
|
$(-469.0)
-
kW-mo/yr
|
$30,635
-
MMBtu
|
- | - | - | - | - | - | |
02 | 2.4154: Avoid rewinding motors more than twice | $722 | $1,569 |
$293
11,137
kWh
|
$429
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.7261: Install timers and/or thermostats | $1,176 | $1,200 |
$1,176
55,979
kWh
|
- | - | - | - | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,310 | $2,478 |
$702
26,963
kWh
|
$608
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $8,100 | $1,000 | - | - | - | - | - |
$13,100
-
lb
|
$(-5,000.0) | - | - | |
06 | 3.4114: Replace city water with recycled water via cooling tower | $1,596 | $3,500 |
$(-144.0)
(-5,569)
kWh
|
$(-141.0)
-
kW-mo/yr
|
- |
$2,381
-
Tgal
|
- | - | - | $(-500.0) | - | |
07 | 4.212: Adopt in-house material generation | $97,778 | $1,000 |
$1,348
51,876
kWh
|
$1,030
-
kW-mo/yr
|
- | - |
$16,200
-
gal
|
- | - | - | $79,200 | |
TOTAL RECOMMENDED | $140,207 | $26,247 |
$2,734
115,767
kWh
|
$1,457
-
kW-mo/yr
|
$30,635
-
MMBtu
|
$2,381
-
Tgal
|
$16,200
-
gal
|
$13,100
-
lb
|
$(-5,000.0) | $(-500.0) | $79,200 | ||
TOTAL IMPLEMENTED | $99,810 | $5,047 |
$2,343
89,976
kWh
|
$2,067
-
kW-mo/yr
|
- | - |
$16,200
-
gal
|
- | - | - | $79,200 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs