Assessment Year | 2024 |
---|---|
Principal Product | meat hotdogs |
NAICS | 311999: All Other Miscellaneous Food Manufacturing |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 349 |
Plant Area |
239,709
ft2
|
Annual Production | 143,000,000
lb
|
Production Hrs. Annual | 7,752
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,387,437 | 28,127,973 |
kWh
|
$0.049 | |
Electricity Demand | $1,142,309 | 55,057 |
kW-mo/yr
|
$20.75 | |
Natural Gas | $1,181,123 | 285,958 |
MMBtu
|
$4.13 | |
Waste Disposal Costs | |||||
Water Usage | $687,004 | 146,522 |
Tgal
|
$4.69 | |
Water Disposal | $663,323 | 137,731 |
Tgal
|
$4.82 | |
TOTAL YEARLY COSTS | $5,061,196 | ||||
RECOMMENDED SAVINGS* | $17,692 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $1,403 | $3,100 |
$939
19,166
kWh
|
- |
$464
-
MMBtu
|
|
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $679 | $620 |
$410
8,734
kWh
|
$269
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $609 | $1,400 |
$609
12,419
kWh
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $7,203 | $14,000 |
$7,203
146,992
kWh
|
- | - | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,952 | $1,511 |
$2,952
60,214
kWh
|
- | - | |
06 | 2.2696: Use excess cold process fluid for industrial cooling needs | $4,846 | $17,804 |
$4,846
98,898
kWh
|
- | - | |
TOTAL RECOMMENDED | $17,692 | $38,435 |
$16,959
346,423
kWh
|
$269
-
kW-mo/yr
|
$464
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs