| Assessment Year | 2026 |
|---|---|
| Principal Product | K-12 School |
| NAICS | 611110: Elementary and Secondary Schools |
| SIC | 8221: Colleges, Universities, and Professional Schools |
| Sales Range | less than $500 k |
| # of Employees | 125 |
| Plant Area |
150,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $75,613 | 867,541 |
kWh
|
$0.087 | |
| Electricity Demand | $25,493 | 2,681 |
kW-mo/yr
|
$9.51 | |
| Electricity Fees | $6,027 | - |
|
- | |
| Natural Gas | $47,855 | 7,957 |
MMBtu
|
$6.01 | |
| Other Energy | $7,726 | 1 |
MMBtu
|
$7,726.00 | |
| Waste Disposal Costs | |||||
| Water Usage | $20,715 | 1,129 |
Tgal
|
$18.35 | |
| TOTAL YEARLY COSTS | $183,429 | ||||
| RECOMMENDED SAVINGS* | $43,928 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,146 | $32,280 |
$17,597
202,268
kWh
|
$5,549
-
kW-mo/yr
|
- | |
| 02 | 2.2211: Use optimum temperature | $5,872 | - | - | - |
$5,872
-
MMBtu
|
|
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,325 | $8,728 |
$4,632
53,236
kWh
|
$693
-
kW-mo/yr
|
- | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $326 | $583 |
$248
2,856
kWh
|
$78
-
kW-mo/yr
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $90 | - |
$56
643
kWh
|
$34
-
kW-mo/yr
|
- | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $63 | $65 |
$37
430
kWh
|
$26
-
kW-mo/yr
|
- | |
| 07 | 2.6125: Keep equipment clean | $2,082 | - |
$1,715
19,707
kWh
|
$368
-
kW-mo/yr
|
- | |
| 08 | 2.7111: Reduce illumination to minimum necessary levels | $213 | - |
$162
1,864
kWh
|
$50
-
kW-mo/yr
|
- | |
| 09 | 2.7134: Use photocell controls | $1,523 | $3,292 |
$1,158
13,305
kWh
|
$365
-
kW-mo/yr
|
- | |
| 10 | 2.7134: Use photocell controls | $941 | - |
$817
9,391
kWh
|
$124
-
kW-mo/yr
|
- | |
| 11 | 2.7135: Install occupancy sensors | $518 | $1,044 |
$394
4,526
kWh
|
$125
-
kW-mo/yr
|
- | |
| 12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $336 | $416 |
$293
3,362
kWh
|
$44
-
kW-mo/yr
|
- | |
| 13 | 2.7241: Install outside air damper / economizer on hvac unit | $96 | - |
$66
757
kWh
|
$30
-
kW-mo/yr
|
- | |
| 14 | 2.7261: Install timers and/or thermostats | $2,790 | $358 |
$2,714
31,200
kWh
|
$76
-
kW-mo/yr
|
- | |
| 15 | 2.7261: Install timers and/or thermostats | $537 | $260 |
$281
3,226
kWh
|
$257
-
kW-mo/yr
|
- | |
| 16 | 2.7444: Close holes and openings in building such as broken windows | $68 | $242 | - | - |
$68
-
MMBtu
|
|
| TOTAL RECOMMENDED | $43,928 | $47,268 |
$30,169
346,770
kWh
|
$7,819
-
kW-mo/yr
|
$5,940
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs