ITAC Assessment: CI0061
ITAC logo
ITAC Assessment: CI0061
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Silicone Hoses
NAICS 326220: Rubber and Plastics Hoses and Belting Manufacturing
SIC 3052: Rubber and Plastics Hose and Belting
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 50,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 4,680
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $154,051 911,528
kWh
Electricity Demand $72,033 4,392
kW-mo/yr
Electricity Fees $14,838 -
Natural Gas $84,650 7,067
MMBtu
LPG $10,920 333
MMBtu
Waste Disposal Costs
Water Usage $21,237 4,284
Tgal
TOTAL YEARLY COSTS $357,729
RECOMMENDED SAVINGS* $270,128 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Primary Product Savings
01 2.4323: Use optimum size and capacity equipment $66,770 $70,000 $4,270
25,269
kWh
- - - $62,500
02 2.9114: Use solar heat to make electricty $64,849 $420,258 $55,289
327,429
kWh
$9,560
-
kW-mo/yr
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $43,650 $800 $37,969
224,788
kWh
$5,681
-
kW-mo/yr
- - -
04 2.2622: Replace existing chiller with high efficiency model $27,840 $28,000 $27,840
164,736
kWh
- - - -
05 2.3141: Use battery storage for demand control $20,734 $162,028 $6,328
37,446
kWh
$14,406
-
kW-mo/yr
- - -
06 2.2511: Insulate bare equipment $17,533 $3,872 - - $17,533
-
MMBtu
- -
07 2.4133: Use most efficient type of electric motors $8,767 $4,500 $7,797
46,138
kWh
$970
-
kW-mo/yr
- - -
08 2.8227: Adjust / maintain fork lift trucks for most efficient operation $6,323 $15,000 $(-3,515.0)
(-20,800)
kWh
$(-1,082.0)
-
kW-mo/yr
- $10,920
-
MMBtu
-
09 2.3132: Recharge batteries on during off-peak demand periods $5,668 $400 - $5,668
-
kW-mo/yr
- - -
10 2.2442: Preheat combustion air with waste heat $4,033 $15,840 - - $4,033
-
MMBtu
- -
11 2.7135: Install occupancy sensors $3,358 $1,500 $2,483
14,695
kWh
$875
-
kW-mo/yr
- - -
12 2.7232: Replace existing hvac unit with high efficiency model $603 $4,000 $603
3,562
kWh
- - - -
TOTAL RECOMMENDED $270,128 $726,198 $139,064
823,263
kWh
$36,078
-
kW-mo/yr
$21,566
-
MMBtu
$10,920
-
MMBtu
$62,500
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs