| Assessment Year | 2025 |
|---|---|
| Principal Product | Gear Boxes |
| NAICS | 333612: Speed Changer, Industrial High-Speed Drive, and Gear Manufacturing |
| SIC | 3566: Speed Changers, Industrial High-Speed Drives, and Gears |
| Sales Range | $50 M to 100M |
| # of Employees | 181 |
| Plant Area |
270,000
ft2
|
| Annual Production | 2,100
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $528,609 | 5,755,436 |
kWh
|
$0.092 |
| Electricity Demand | $1 | 18,085 |
kW-mo/yr
|
$0.000 |
| Electricity Fees | $8,014 | - |
|
- |
| Natural Gas | $202,933 | 43,004 |
MMBtu
|
$4.72 |
| Other Gas | $23,188 | 1 |
MMBtu
|
$23,188.49 |
| TOTAL YEARLY COSTS | $762,745 | |||
| RECOMMENDED SAVINGS* | $46,302 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7232: Replace existing hvac unit with high efficiency model | $33,104 | $284,789 |
$13,327
144,860
kWh
|
$15,000 |
$4,777
-
MMBtu
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,989 | $320 |
$4,989
54,231
kWh
|
- | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $1,020 | $3,218 |
$1,020
11,090
kWh
|
- | - | |
| 04 | 2.6231: Utilize controls to operate equipment only when needed | $3,238 | $3,797 | - | - |
$3,238
-
MMBtu
|
|
| 05 | 2.7134: Use photocell controls | $121 | $286 |
$121
131
kWh
|
- | - | |
| 06 | 2.7135: Install occupancy sensors | $2,030 | $3,314 |
$2,030
22,061
kWh
|
- | - | |
| 07 | 4.821: Pay bills on time to avoid late fees | $1,800 | - | - | $1,800 | - | |
| TOTAL RECOMMENDED | $46,302 | $295,724 |
$21,487
232,372
kWh
|
$16,800 |
$8,015
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs