| Assessment Year | 2026 |
|---|---|
| Principal Product | Paper Clips |
| NAICS | 332618: Other Fabricated Wire Product Manufacturing |
| SIC | 3496: Miscellaneous Fabricated Wire Products |
| Sales Range | $100 M to 500M |
| # of Employees | 300 |
| Plant Area |
925,000
ft2
|
| Annual Production | 1,000,000,000
units
|
| Production Hrs. Annual | 3,750
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $555,959 | 7,821,600 |
kWh
|
$0.071 | |
| Electricity Demand | $304,972 | 21,364 |
kW-mo/yr
|
$14.28 | |
| Electricity Fees | $39,510 | - |
|
- | |
| Natural Gas | $136,960 | 15,852 |
MMBtu
|
$8.64 | |
| LPG | $38,400 | 1,873 |
MMBtu
|
$20.50 | |
| Waste Disposal Costs | |||||
| Water Usage | $14,632 | 1,427 |
Tgal
|
$10.25 | |
| Water Disposal | $11,489 | 1,427 |
Tgal
|
$8.05 | |
| TOTAL YEARLY COSTS | $1,101,922 | ||||
| RECOMMENDED SAVINGS* | $711,718 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7243: Improve air circulation with destratification fans / other methods | $29,766 | $61,672 |
$29,766
418,647
kWh
|
- | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13,520 | - |
$13,520
190,154
kWh
|
- | - | - | |
| 03 | 2.7221: Lower temperature during the winter season and vice-versa | $24,902 | - | - |
$24,902
-
MMBtu
|
- | - | |
| 04 | 4.231: Purchase equipment instead of leasing | $607,068 | $889,000 |
$(-15,307.0)
(-215,294)
kWh
|
- |
$38,400
-
MMBtu
|
$583,975 | |
| 05 | 2.7261: Install timers and/or thermostats | $34,362 | $147,620 |
$34,362
483,288
kWh
|
- | - | - | |
| 06 | 2.3311: Replace dc equipment with ac equipment | $2,100 | $26,537 |
$2,100
29,540
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $711,718 | $1,124,829 |
$64,441
906,335
kWh
|
$24,902
-
MMBtu
|
$38,400
-
MMBtu
|
$583,975 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs