| Assessment Year | 2005 |
|---|---|
| Principal Product | stamped parts |
| NAICS | 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive) |
| SIC | 3469: Metal Stampings, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
348,275
ft2
|
| Annual Production | 14,000,000
pieces
|
| Production Hrs. Annual | 4,896
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $333,130 | 7,514,584 |
kWh
|
$0.044 |
| Electricity Demand | $57,384 | 17,779 |
kW-mo/yr
|
$3.23 |
| Electricity Fees | $166,311 | - |
|
- |
| Natural Gas | $163,696 | 21,918 |
MMBtu
|
$7.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $171,460 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $113,331 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.5111: Convert from indirect to direct fired systems | $85,531 | $33,636 | - | - | - |
$85,531
-
MMBtu
|
|
| 02 | 2.2135: Repair and eliminate steam leaks | $30,473 | $134 | - | - | - |
$30,473
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,820 | $25,845 |
$9,116
233,580
kWh
|
$1,828
-
kW-mo/yr
|
$3,876 | - | |
| 04 | 2.2136: Install / repair insulation on steam lines | $10,885 | $7,085 | - | - | - |
$10,885
-
MMBtu
|
|
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,540 | $6,210 |
$2,956
75,753
kWh
|
$1,185
-
kW-mo/yr
|
$1,399 | - | |
| 06 | 3.6124: Burn waste oil for heat | $4,922 | $9,172 | - | - | - |
$4,922
-
MMBtu
|
|
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,263 | - |
$3,094
79,288
kWh
|
- | $1,169 | - | |
| 08 | 2.2511: Insulate bare equipment | $3,550 | $1,054 | - | - | - |
$3,550
-
MMBtu
|
|
| 09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,500 | $11,608 |
$2,541
65,098
kWh
|
- | $959 | - | |
| 10 | 2.7124: Make a practice of turning off lights when not needed | $2,881 | - |
$2,091
53,582
kWh
|
- | $790 | - | |
| 11 | 2.6218: Turn off equipment when not in use | $2,286 | - | - | - | - |
$2,286
-
MMBtu
|
|
| 12 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,799 | $203 |
$1,305
33,450
kWh
|
- | $494 | - | |
| 13 | 2.4221: Install compressor air intakes in coolest locations | $515 | $1,158 |
$308
7,889
kWh
|
$73
-
kW-mo/yr
|
$134 | - | |
| 14 | 2.7261: Install timers and/or thermostats | $495 | $236 |
$359
9,200
kWh
|
- | $136 | - | |
| TOTAL RECOMMENDED | $171,460 | $96,341 |
$21,770
557,840
kWh
|
$3,086
-
kW-mo/yr
|
$8,957 |
$137,647
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $113,331 | $60,535 |
$14,301
366,450
kWh
|
$1,828
-
kW-mo/yr
|
$5,835 |
$91,367
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs