ITAC Assessment: MS0188
ITAC logo
ITAC Assessment: MS0188
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Wiring Harnesses
NAICS
n/a
SIC 3694: Electrical Equipment for Internal Combustion Engines
Sales Range $10
M
to 50
M
# of Employees 220
Plant Area 50,000
ft2
Annual Production 400,000
pieces
Production Hrs. Annual 3,800
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $42,340 694,560
kWh
Electricity Demand $58 1,704
kW-mo/yr
Electricity Fees $6,434 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,545 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.6214: Shut off pilots in standby equipment $134 $27 - - $134
-
MMBtu
-
02 2.7444: Close holes and openings in building such as broken windows $62 $88 $45
869
kWh
$17 - -
03 2.7261: Install timers and/or thermostats $1,408 $1,310 $1,032
19,797
kWh
$376 - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $7,583 $14,235 $5,559
106,646
kWh
$2,024 - -
05 3.5315: Lease / purchase baler; sell cardboard to recycler $8,358 $6,500 - - - $8,358
-
lb
TOTAL RECOMMENDED $17,545 $22,160 $6,636
127,312
kWh
$2,417 $134
-
MMBtu
$8,358
-
lb
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs