Assessment Year | 2001 |
---|---|
Principal Product | Automotive Wiring Connectors |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 74 |
Plant Area |
35,000
ft2
|
Annual Production | 230,000,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $158,489 | 2,861,832 |
kWh
|
$0.055 |
Electricity Demand | $19,017 | 5,571 |
kW-mo/yr
|
$3.41 |
Electricity Fees | $7,368 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,661 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $3,051 | $348 |
$2,362
68,746
kWh
|
- | $689 | - | |
02 | 2.7261: Install timers and/or thermostats | $571 | $375 |
$441
8,466
kWh
|
- | $130 | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $14,523 | $6,599 |
$7,924
42,790
kWh
|
- | $6,599 | - | |
04 | 2.7261: Install timers and/or thermostats | $702 | $875 |
$542
10,604
kWh
|
- | $160 | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,464 | $2,153 |
$1,127
32,804
kWh
|
$6
-
kW-mo/yr
|
$331 | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $946 | $2,073 |
$731
14,026
kWh
|
- | $215 | - | |
07 | 2.4314: Use synthetic lubricant | $44 | $17 |
$21
406
kWh
|
- | $6 |
$17
-
gal
|
|
08 | 4.512: Condense operation into one building | $56 | $25 | - | - | $56 | - | |
09 | 3.5244: Recover metals from casting sand | $9,304 | $32 | - | - | - |
$9,304
-
gal
|
|
TOTAL RECOMMENDED | $30,661 | $12,497 |
$13,148
177,842
kWh
|
$6
-
kW-mo/yr
|
$8,186 |
$9,321
-
gal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs