| Assessment Year | 2000 |
|---|---|
| Principal Product | Wooden Office Furniture |
| NAICS |
n/a
|
| SIC | 2521: Wood Office Furniture |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
109,000
ft2
|
| Annual Production | 200,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $138,199 | 2,852,872 |
kWh
|
$0.048 |
| Electricity Demand | $28,489 | 7,010 |
kW-mo/yr
|
$4.06 |
| Electricity Fees | $(-10,544.0) | - |
|
- |
| Natural Gas | $10,591 | 1,862 |
MMBtu
|
$5.69 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $44,937 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $190 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6214: Shut off pilots in standby equipment | $190 | $70 | - | - | - |
$190
-
MMBtu
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $551 | $222 |
$517
11,430
kWh
|
$86
-
kW-mo/yr
|
$(-52.0) | - | - | |
| 03 | 2.2437: Recover waste heat from equipment | $1,903 | $3,464 | - | - | - |
$1,903
-
MMBtu
|
- | |
| 04 | 2.7261: Install timers and/or thermostats | $311 | $472 |
$340
7,620
kWh
|
- | $(-29.0) | - | - | |
| 05 | 2.2136: Install / repair insulation on steam lines | $1,157 | $376 |
$1,267
28,136
kWh
|
- | $(-110.0) | - | - | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $11,439 | $7,938 |
$11,400
249,707
kWh
|
$1,180
-
kW-mo/yr
|
$(-1,141.0) | - | - | |
| 07 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $29,386 | $2,399 | - | - | - | - | $29,386 | |
| TOTAL RECOMMENDED | $44,937 | $14,941 |
$13,524
296,893
kWh
|
$1,266
-
kW-mo/yr
|
$(-1,332.0) |
$2,093
-
MMBtu
|
$29,386 | ||
| TOTAL IMPLEMENTED | $190 | $70 | - | - | - |
$190
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs