ITAC Assessment: MS0166
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Wooden Office Furniture
NAICS
n/a
SIC 2521: Wood Office Furniture
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 109,000
ft2
Annual Production 200,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $138,199 2,852,872
kWh
Electricity Demand $28,489 7,010
kW-mo/yr
Electricity Fees $(-10,544.0) -
Natural Gas $10,591 1,862
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,937 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $190

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.6214: Shut off pilots in standby equipment $190 $70 - - - $190
-
MMBtu
-
02 2.4221: Install compressor air intakes in coolest locations $551 $222 $517
11,430
kWh
$86
-
kW-mo/yr
$(-52.0) - -
03 2.2437: Recover waste heat from equipment $1,903 $3,464 - - - $1,903
-
MMBtu
-
04 2.7261: Install timers and/or thermostats $311 $472 $340
7,620
kWh
- $(-29.0) - -
05 2.2136: Install / repair insulation on steam lines $1,157 $376 $1,267
28,136
kWh
- $(-110.0) - -
06 2.4239: Eliminate or reduce compressed air usage $11,439 $7,938 $11,400
249,707
kWh
$1,180
-
kW-mo/yr
$(-1,141.0) - -
07 3.2123: Convert to high volume low pressure (hvlp) paint guns $29,386 $2,399 - - - - $29,386
TOTAL RECOMMENDED $44,937 $14,941 $13,524
296,893
kWh
$1,266
-
kW-mo/yr
$(-1,332.0) $2,093
-
MMBtu
$29,386
TOTAL IMPLEMENTED $190 $70 - - - $190
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs