Assessment Year | 2001 |
---|---|
Principal Product | Solenoids |
NAICS |
n/a
|
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 280 |
Plant Area |
104,000
ft2
|
Annual Production | 10,000
pieces
|
Production Hrs. Annual | 4,125
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $57,300 | 2,583,300 |
kWh
|
$0.022 |
Electricity Demand | $110,104 | 7,944 |
kW-mo/yr
|
$13.86 |
Natural Gas | $14,956 | 1,778 |
MMBtu
|
$8.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $42,049 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,955 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $29,813 | $10,710 |
$66
2,975
kWh
|
$118
-
kW-mo/yr
|
$30,129
-
Tgal
|
$(-500.0)
-
gal
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,975 | $13,704 |
$3,581
162,750
kWh
|
$7,394
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $980 | $414 |
$308
14,000
kWh
|
$672
-
kW-mo/yr
|
- | - | - | |
04 | 3.4116: Meter recycled water (to reduce sewer charges) | $281 | $500 | - | - | - | - | $281 | |
TOTAL RECOMMENDED | $42,049 | $25,328 |
$3,955
179,725
kWh
|
$8,184
-
kW-mo/yr
|
$30,129
-
Tgal
|
$(-500.0)
-
gal
|
$281 | ||
TOTAL IMPLEMENTED | $11,955 | $14,118 |
$3,889
176,750
kWh
|
$8,066
-
kW-mo/yr
|
- | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs