Assessment Year | 2000 |
---|---|
Principal Product | Compression Molded Drain Pans |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 65 |
Plant Area |
840,000
ft2
|
Annual Production | 840,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $49,435 | 1,315,944 |
kWh
|
$0.038 |
Electricity Demand | $23,981 | 3,336 |
kW-mo/yr
|
$7.19 |
Electricity Fees | $3,698 | - |
|
- |
Natural Gas | $1,675 | 301 |
MMBtu
|
$5.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,130 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,866 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $2,236 | $2,610 | - | - | $2,236 | - | - | |
02 | 2.7261: Install timers and/or thermostats | $50 | $119 |
$49
1,465
kWh
|
- | $1 | - | - | |
03 | 2.7134: Use photocell controls | $276 | $222 |
$272
8,206
kWh
|
- | $4 | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $635 | $89 |
$328
9,965
kWh
|
$297
-
kW-mo/yr
|
$10 | - | - | |
05 | 2.7135: Install occupancy sensors | $192 | $346 |
$189
5,569
kWh
|
- | $3 | - | - | |
06 | 2.7241: Install outside air damper / economizer on hvac unit | $4,736 | $4,200 |
$4,666
140,680
kWh
|
- | $70 | - | - | |
07 | 2.2511: Insulate bare equipment | $2,189 | $2,446 |
$2,157
46,600
kWh
|
- | $32 | - | - | |
08 | 3.7196: Use re-usable filters | $4,800 | $648 | - | - | - | - | $4,800 | |
09 | 4.821: Pay bills on time to avoid late fees | $16 | - | - | - | - | - | $16 | |
10 | 4.444: Install system to collect scrap | $4,000 | $5,246 | - | - | - | $4,000 | - | |
TOTAL RECOMMENDED | $19,130 | $15,926 |
$7,661
212,485
kWh
|
$297
-
kW-mo/yr
|
$2,356 | $4,000 | $4,816 | ||
TOTAL IMPLEMENTED | $8,866 | $6,013 |
$49
1,465
kWh
|
- | $1 | $4,000 | $4,816 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs