Assessment Year | 2021 |
---|---|
Principal Product | wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $1 M to 5M |
# of Employees | 3 |
Plant Area |
200,000
ft2
|
Annual Production | 365,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $28,974 | 939,520 |
kWh
|
$0.031 |
Electricity Demand | $50,308 | 2,301 |
kW-mo/yr
|
$21.86 |
Electricity Fees | $1,167 | - |
|
- |
TOTAL YEARLY COSTS | $80,449 | |||
RECOMMENDED SAVINGS* | $91,746 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,514 | $444 |
$771
24,878
kWh
|
$743
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,021 | $2,633 |
$556
17,945
kWh
|
$1,465
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7135: Install occupancy sensors | $231 | $650 |
$231
7,437
kWh
|
- | - | - | - | - | |
04 | 2.6242: Minimize operation of equipment maintained in standby condition | $85 | $285 |
$85
2,754
kWh
|
- | - | - | - | - | |
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $26,160 | $9,000 |
$13,306
429,240
kWh
|
$12,854
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.5194: Redesign process | $16,187 | $25,000 |
$3,259
105,120
kWh
|
$3,148
-
kW-mo/yr
|
- | - | $9,780 | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $10,415 | $13,780 |
$(-48.0)
(-1,560)
kWh
|
$(-197.0)
-
kW-mo/yr
|
- |
$1,560
-
gal
|
$9,100 | - | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $21,003 | - |
$1,629
52,560
kWh
|
$1,574
-
kW-mo/yr
|
- | - | - | $17,800 | |
09 | 3.4159: Replace treated water with well / surface water | $13,774 | $4,000 |
$(-361.0)
(-11,638)
kWh
|
$(-1,465.0)
-
kW-mo/yr
|
$15,600
-
Tgal
|
- | - | - | |
10 | 2.7224: Reduce space conditioning during non-working hours | $356 | $78 |
$356
11,468
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $91,746 | $55,870 |
$19,784
638,204
kWh
|
$18,122
-
kW-mo/yr
|
$15,600
-
Tgal
|
$1,560
-
gal
|
$18,880 | $17,800 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs