| Assessment Year | 2011 |
|---|---|
| Principal Product | Thermoformed plastic parts |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 65 |
| Plant Area |
76,000
ft2
|
| Annual Production | 150,000,000
lb
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $75,324 | 1,970,453 |
kWh
|
$0.038 |
| Electricity Demand | $193,320 | 10,171 |
kW-mo/yr
|
$19.01 |
| Electricity Fees | $1,806 | - |
|
- |
| Natural Gas | $16,518 | 2,253 |
MMBtu
|
$7.33 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,230 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,250 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,700 | $1,000 | - |
$4,700
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,390 | $190 |
$610
14,300
kWh
|
$780
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,420 | $9,240 |
$2,270
42,900
kWh
|
$1,970
-
kW-mo/yr
|
- | $140 | - | $40 | |
| 04 | 2.9114: Use solar heat to make electricty | $2,980 | $24,500 |
$1,580
15,600
kWh
|
- | - | - | $1,400 | - | |
| 05 | 2.7243: Improve air circulation with destratification fans / other methods | $740 | $1,470 |
$(-40.0)
(-900)
kWh
|
$(-20.0)
-
kW-mo/yr
|
$800
-
MMBtu
|
- | - | - | |
| TOTAL RECOMMENDED | $14,230 | $36,400 |
$4,420
71,900
kWh
|
$7,430
-
kW-mo/yr
|
$800
-
MMBtu
|
$140 | $1,400 | $40 | ||
| TOTAL IMPLEMENTED | $11,250 | $11,900 |
$2,840
56,300
kWh
|
$7,430
-
kW-mo/yr
|
$800
-
MMBtu
|
$140 | - | $40 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs