ITAC Assessment: CO0650
ITAC logo
ITAC Assessment: CO0650
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Thermoformed plastic parts
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 65
Plant Area 76,000
ft2
Annual Production 150,000,000
lb
Production Hrs. Annual 4,160
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $75,324 1,970,453
kWh
Electricity Demand $193,320 10,171
kW-mo/yr
Electricity Fees $1,806 -
Natural Gas $16,518 2,253
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,230 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,250

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,700 $1,000 - $4,700
-
kW-mo/yr
- - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,390 $190 $610
14,300
kWh
$780
-
kW-mo/yr
- - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,420 $9,240 $2,270
42,900
kWh
$1,970
-
kW-mo/yr
- $140 - $40
04 2.9114: Use solar heat to make electricty $2,980 $24,500 $1,580
15,600
kWh
- - - $1,400 -
05 2.7243: Improve air circulation with destratification fans / other methods $740 $1,470 $(-40.0)
(-900)
kWh
$(-20.0)
-
kW-mo/yr
$800
-
MMBtu
- - -
TOTAL RECOMMENDED $14,230 $36,400 $4,420
71,900
kWh
$7,430
-
kW-mo/yr
$800
-
MMBtu
$140 $1,400 $40
TOTAL IMPLEMENTED $11,250 $11,900 $2,840
56,300
kWh
$7,430
-
kW-mo/yr
$800
-
MMBtu
$140 - $40
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs