Assessment Year | 1999 |
---|---|
Principal Product | Automotive stampings, wheel covers and rings |
NAICS |
n/a
|
SIC | 3465: Automotive Stampings |
Sales Range | $10 M to 50M |
# of Employees | 137 |
Plant Area |
258,243
ft2
|
Annual Production | 8,000,000
pieces
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $429,701 | 9,262,017 |
kWh
|
$0.046 |
Electricity Demand | $82,958 | 29,904 |
kW-mo/yr
|
$2.77 |
Electricity Fees | $42,083 | - |
|
- |
Natural Gas | $220,705 | 72,536 |
MMBtu
|
$3.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $85,068 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $69,575 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,085 | $881 |
$21,323
486,811
kWh
|
- | $(-1,238.0) | - | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,403 | $360 |
$970
22,274
kWh
|
$348
-
kW-mo/yr
|
$85 | - | - | - | - | |
03 | 2.7261: Install timers and/or thermostats | $534 | $236 |
$567
12,896
kWh
|
- | $(-33.0) | - | - | - | - | |
04 | 3.4111: Use closed cycle process to minimize waste water production | $1,791 | $5,795 |
$129
2,931
kWh
|
- | $(-8.0) | - |
$1,670
-
Tgal
|
- | - | |
05 | 3.6124: Burn waste oil for heat | $12,299 | $16,435 | - | - | - |
$4,299
-
MMBtu
|
- |
$8,000
-
gal
|
- | |
06 | 4.125: | $48,956 | $6,286 |
$67
1,758
kWh
|
- | - |
$12,969
-
MMBtu
|
$920
-
Tgal
|
- | $35,000 | |
TOTAL RECOMMENDED | $85,068 | $29,993 |
$23,056
526,670
kWh
|
$348
-
kW-mo/yr
|
$(-1,194.0) |
$17,268
-
MMBtu
|
$2,590
-
Tgal
|
$8,000
-
gal
|
$35,000 | ||
TOTAL IMPLEMENTED | $69,575 | $7,403 |
$21,957
501,465
kWh
|
- | $(-1,271.0) |
$12,969
-
MMBtu
|
$920
-
Tgal
|
- | $35,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs