Assessment Year | 1999 |
---|---|
Principal Product | Waste Handling and Recycling Equipment |
NAICS |
n/a
|
SIC | 3589: Service Industry Machinery, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 398 |
Plant Area |
132,613
ft2
|
Annual Production | 10,328
pieces
|
Production Hrs. Annual | 4,300
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $173,121 | 4,333,822 |
kWh
|
$0.040 |
Electricity Demand | $58,677 | 12,379 |
kW-mo/yr
|
$4.74 |
Electricity Fees | $71,910 | - |
|
- |
Natural Gas | $76,163 | 13,369 |
MMBtu
|
$5.70 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,780 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,780 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $441 | $94 |
$209
7,913
kWh
|
$104
-
kW-mo/yr
|
$128 | - | - | |
02 | 2.7221: Lower temperature during the winter season and vice-versa | $3,291 | $149 | - | - | - |
$3,291
-
MMBtu
|
- | |
03 | 2.7261: Install timers and/or thermostats | $905 | $472 |
$567
21,395
kWh
|
- | $338 | - | - | |
04 | 3.7196: Use re-usable filters | $143 | $160 | - | - | - | - | $143 | |
TOTAL RECOMMENDED | $4,780 | $875 |
$776
29,308
kWh
|
$104
-
kW-mo/yr
|
$466 |
$3,291
-
MMBtu
|
$143 | ||
TOTAL IMPLEMENTED | $4,780 | $875 |
$776
29,308
kWh
|
$104
-
kW-mo/yr
|
$466 |
$3,291
-
MMBtu
|
$143 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs