ITAC Assessment: UW2409
ITAC logo
ITAC Assessment: UW2409
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Beverage Manufacturing
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 246
Plant Area 283,711
ft2
Annual Production 217,000,000
units
Production Hrs. Annual 7,488
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $628,297 8,925,880
kWh
Electricity Demand $298,295 23,834
kW-mo/yr
Electricity Fees $112,996 -
Natural Gas $548,221 62,636
MMBtu
Waste Disposal Costs
Water Usage $1,149,563 93,810
Tgal
Water Disposal $280,448 93,810
Tgal
TOTAL YEARLY COSTS $3,017,820
RECOMMENDED SAVINGS* $1,452,455 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Natural Gas Savings Water Usage Savings
01 2.2113: Repair or replace steam traps $240,871 $7,750 $240,871
-
MMBtu
-
02 2.2135: Repair and eliminate steam leaks $1,927 $2,080 $1,927
-
MMBtu
-
03 3.4113: Treat and reuse rinse waters $1,034,601 $300,000 - $1,034,601
-
Tgal
04 4.661: Level zero – install control systems for existing equipment $16,446 $18,600 $16,446
-
MMBtu
-
05 2.1224: Replace boiler $61,679 $155,400 $61,679
-
MMBtu
-
06 4.432: Cross-train personnel to avoid lost time $72,261 $271,830 $72,261
-
MMBtu
-
07 2.2124: Install de-aerator in place of condensate tank $24,670 $223,625 $24,670
-
MMBtu
-
TOTAL RECOMMENDED $1,452,455 $979,285 $417,854
-
MMBtu
$1,034,601
-
Tgal
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Natural Gas Savings Water Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs