Assessment Year | 2024 |
---|---|
Principal Product | Beverage Manufacturing |
NAICS | 312111: Soft Drink Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $10 M to 50M |
# of Employees | 246 |
Plant Area |
283,711
ft2
|
Annual Production | 217,000,000
units
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $628,297 | 8,925,880 |
kWh
|
$0.070 | |
Electricity Demand | $298,295 | 23,834 |
kW-mo/yr
|
$12.52 | |
Electricity Fees | $112,996 | - |
|
- | |
Natural Gas | $548,221 | 62,636 |
MMBtu
|
$8.75 | |
Waste Disposal Costs | |||||
Water Usage | $1,149,563 | 93,810 |
Tgal
|
$12.25 | |
Water Disposal | $280,448 | 93,810 |
Tgal
|
$2.99 | |
TOTAL YEARLY COSTS | $3,017,820 | ||||
RECOMMENDED SAVINGS* | $1,452,455 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Natural Gas Savings | Water Usage Savings |
---|---|---|---|---|---|---|
01 | 2.2113: Repair or replace steam traps | $240,871 | $7,750 |
$240,871
-
MMBtu
|
- | |
02 | 2.2135: Repair and eliminate steam leaks | $1,927 | $2,080 |
$1,927
-
MMBtu
|
- | |
03 | 3.4113: Treat and reuse rinse waters | $1,034,601 | $300,000 | - |
$1,034,601
-
Tgal
|
|
04 | 4.661: Level zero – install control systems for existing equipment | $16,446 | $18,600 |
$16,446
-
MMBtu
|
- | |
05 | 2.1224: Replace boiler | $61,679 | $155,400 |
$61,679
-
MMBtu
|
- | |
06 | 4.432: Cross-train personnel to avoid lost time | $72,261 | $271,830 |
$72,261
-
MMBtu
|
- | |
07 | 2.2124: Install de-aerator in place of condensate tank | $24,670 | $223,625 |
$24,670
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $1,452,455 | $979,285 |
$417,854
-
MMBtu
|
$1,034,601
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Natural Gas Savings | Water Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs