Assessment Year | 1997 |
---|---|
Principal Product | Noncurrent-Carrying Wiring Boxes |
NAICS |
n/a
|
SIC | 3644: Noncurrent-Carrying Wiring Devices |
Sales Range | $50 M to 100M |
# of Employees | 325 |
Plant Area |
165,000
ft2
|
Annual Production | 43,700,000
lb
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $290,786 | 5,445,487 |
kWh
|
$0.053 |
Electricity Demand | $40,251 | 11,735 |
kW-mo/yr
|
$3.43 |
Electricity Fees | $20,744 | - |
|
- |
Natural Gas | $173,925 | 47,935 |
MMBtu
|
$3.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $59,939 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,615 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $4,329 | $5,125 |
$3,850
101,993
kWh
|
- | $479 | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,624 | $8,079 |
$4,150
88,511
kWh
|
$459
-
kW-mo/yr
|
$1,015 | - | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $292 | $577 |
$224
6,448
kWh
|
$33
-
kW-mo/yr
|
$35 | - | - | - | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $4,931 | $2,350 | - | - | - |
$4,931
-
MMBtu
|
- | - | - | |
05 | 3.4115: Recover and reuse cooling water | $37,143 | $7,666 |
$(-5,278.0)
(-153,576)
kWh
|
$(-812.0)
-
kW-mo/yr
|
- | - |
$23,222
-
Tgal
|
- |
$20,011
-
Tgal
|
|
06 | 3.6124: Burn waste oil for heat | $958 | $1,995 | - | - | - |
$958
-
MMBtu
|
- | - | - | |
07 | 4.511: Expand operations into unused space | $5,005 | $672 | - | - | - | - | - | $5,005 | - | |
08 | 4.515: Install shelves / racks to utilize unused space | $1,657 | $1,256 | - | - | - | - | - | $1,657 | - | |
TOTAL RECOMMENDED | $59,939 | $27,720 |
$2,946
43,376
kWh
|
$(-320.0)
-
kW-mo/yr
|
$1,529 |
$5,889
-
MMBtu
|
$23,222
-
Tgal
|
$6,662 |
$20,011
-
Tgal
|
||
TOTAL IMPLEMENTED | $16,615 | $15,132 |
$8,000
190,504
kWh
|
$459
-
kW-mo/yr
|
$1,494 | - | - | $6,662 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs