Assessment Year | 1995 |
---|---|
Principal Product | Boilers and Water Treatment Systems |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
52,000
ft2
|
Annual Production | 1,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $124,778 | 1,735,053 |
kWh
|
$0.072 |
Natural Gas | $29,969 | 7,530 |
MMBtu
|
$3.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,725 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,555 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $686 | $2,455 |
$686
12,896
kWh
|
- | |
02 | 2.7122: Disconnect ballasts | $1,005 | $200 |
$1,005
19,637
kWh
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $407 | $321 |
$407
7,620
kWh
|
- | |
04 | 2.2437: Recover waste heat from equipment | $3,696 | $3,080 | - |
$3,696
-
MMBtu
|
|
05 | 2.7261: Install timers and/or thermostats | $818 | $730 |
$818
18,757
kWh
|
- | |
06 | 2.7231: Use radiant heater for spot heating | $8,484 | $21,600 | - |
$8,484
-
MMBtu
|
|
07 | 2.7124: Make a practice of turning off lights when not needed | $629 | - |
$629
14,361
kWh
|
- | |
TOTAL RECOMMENDED | $15,725 | $28,386 |
$3,545
73,271
kWh
|
$12,180
-
MMBtu
|
||
TOTAL IMPLEMENTED | $6,555 | $4,331 |
$2,859
60,375
kWh
|
$3,696
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs