| Assessment Year | 1995 |
|---|---|
| Principal Product | Cast Aluminum Parts |
| NAICS |
n/a
|
| SIC | 3365: Aluminum Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 290 |
| Plant Area |
80,000
ft2
|
| Annual Production | 1,500,000
pieces
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $322,147 | 6,166,178 |
kWh
|
$0.052 |
| Natural Gas | $353,495 | 126,511 |
MMBtu
|
$2.79 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $177,382 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $20,542 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $16,206 | $7,500 |
$16,206
-
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $4,336 | $2,170 |
$4,336
94,959
kWh
|
- | |
| 03 | 2.7261: Install timers and/or thermostats | $393 | $730 |
$393
12,603
kWh
|
- | |
| 04 | 2.2437: Recover waste heat from equipment | $3,552 | $5,640 | - |
$3,552
-
MMBtu
|
|
| 05 | 2.1213: Direct warmest air to combustion intake | $152,895 | $101,700 | - |
$152,895
-
MMBtu
|
|
| TOTAL RECOMMENDED | $177,382 | $117,740 |
$20,935
107,562
kWh
|
$156,447
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $20,542 | $9,670 |
$20,542
94,959
kWh
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs