ITAC Assessment: MS0028
ITAC logo
ITAC Assessment: MS0028
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product processed catfish
NAICS
n/a
SIC 2092: Prepared Fresh or Frozen Fish and Seafoods
Sales Range $50
M
to 100
M
# of Employees 450
Plant Area 76,000
ft2
Annual Production 60,000,000
lb
Production Hrs. Annual 2,400
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $531,056 8,099,942
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,063 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $225

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,307 $3,535 $2,307
46,893
kWh
02 2.4133: Use most efficient type of electric motors $2,151 $16,575 $2,151
43,376
kWh
03 2.7261: Install timers and/or thermostats $3,234 $450 $3,234
77,081
kWh
04 2.7261: Install timers and/or thermostats $1,146 $1,050 $1,146
22,567
kWh
05 2.7444: Close holes and openings in building such as broken windows $225 $100 $225
5,275
kWh
TOTAL RECOMMENDED $9,063 $21,710 $9,063
195,192
kWh
TOTAL IMPLEMENTED $225 $100 $225
5,275
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs