ITAC Assessment: MO0284
ITAC logo
ITAC Assessment: MO0284
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Pressure Switches, Gas and Oil Valves
NAICS
n/a
SIC 3822: Automatic Controls for Regulating Residential and Commercial Environments and Appliances
Sales Range $10
M
to 50
M
# of Employees 285
Plant Area 80,000
ft2
Annual Production 1,500,000
pieces
Production Hrs. Annual 6,864
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $153,222 4,644,490
kWh
Electricity Demand $60,818 954
kW-mo/yr
Electricity Fees $10,299 -
Natural Gas $13,265 1,132
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,304 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,677 $8,150 $2,848
80,891
kWh
$829
-
kW-mo/yr
- -
02 2.4133: Use most efficient type of electric motors $3,696 $4,565 $2,931
83,236
kWh
$765
-
kW-mo/yr
- -
03 2.4221: Install compressor air intakes in coolest locations $1,921 $210 $1,538
43,669
kWh
$383
-
kW-mo/yr
- -
04 3.5315: Lease / purchase baler; sell cardboard to recycler $540 - - - $540
-
lb
-
05 4.446: Automate finishing process $6,370 $900 - - - $6,370
06 4.423: Move product using mechanical means $9,100 $6,000 - - - $9,100
TOTAL RECOMMENDED $25,304 $19,825 $7,317
207,796
kWh
$1,977
-
kW-mo/yr
$540
-
lb
$15,470
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs