| Assessment Year | 2000 |
|---|---|
| Principal Product | Uniforms |
| NAICS |
n/a
|
| SIC | 2389: Apparel and Accessories, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 200 |
| Plant Area |
35,000
ft2
|
| Annual Production | 25,720
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $39,620 | 639,508 |
kWh
|
$0.062 |
| Electricity Demand | $3,649 | 146 |
kW-mo/yr
|
$24.99 |
| Electricity Fees | $6,619 | - |
|
- |
| Natural Gas | $10,498 | 1,645 |
MMBtu
|
$6.38 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,861 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,395 | $15,233 |
$5,872
81,184
kWh
|
$523
-
kW-mo/yr
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $987 | $845 |
$912
12,603
kWh
|
$75
-
kW-mo/yr
|
- | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $407 | $122 |
$382
5,275
kWh
|
$25
-
kW-mo/yr
|
- | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $407 | $40 |
$382
5,275
kWh
|
$25
-
kW-mo/yr
|
- | - | |
| 05 | 3.7198: Reduce / eliminate use of disposable product | $338 | $240 | - | - |
$338
-
lb
|
- | |
| 06 | 3.5313: Increase amount of waste recovered for resale | $836 | - | - | - |
$836
-
lb
|
- | |
| 07 | 4.445: Install equipment to move product | $4,380 | $338 | - | - | - | $4,380 | |
| 08 | 4.446: Automate finishing process | $5,111 | $1,400 | - | - | - | $5,111 | |
| TOTAL RECOMMENDED | $18,861 | $18,218 |
$7,548
104,337
kWh
|
$648
-
kW-mo/yr
|
$1,174
-
lb
|
$9,491 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs