ITAC Assessment: MO0160
ITAC logo
ITAC Assessment: MO0160
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Cosmetics and Toiletries
NAICS
n/a
SIC 2844: Perfumes, Cosmetics, and Other Toilet Preparations
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 52,300
ft2
Annual Production 27,400,000
pieces
Production Hrs. Annual 4,400
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $146,237 2,146,835
kWh
Natural Gas $45,062 10,831
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,260 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,090

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Liquid (haz) Savings
01 2.4133: Use most efficient type of electric motors $2,546 $5,913 $2,546
38,101
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $39 - $39
586
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $322 - $322
4,982
kWh
- -
04 2.1233: Analyze flue gas for proper air/fuel ratio $1,771 $1,195 - $1,771
-
MMBtu
-
05 2.4221: Install compressor air intakes in coolest locations $3,198 $1,390 $3,198
46,893
kWh
- -
06 2.1311: Replace electrically-operated equipment with fossil fuel equipment $690 $1,430 $940
14,068
kWh
$(-250.0)
-
MMBtu
-
07 2.7447: Install vinyl strip / high speed / air curtain doors $1,480 $2,330 - $1,480
-
MMBtu
-
08 2.2514: Cover open tanks $174 $275 - $174
-
MMBtu
-
09 3.1161: Eliminate/reduce an operation $4,040 $8,000 - - $4,040
-
gal
TOTAL RECOMMENDED $14,260 $20,533 $7,045
104,630
kWh
$3,175
-
MMBtu
$4,040
-
gal
TOTAL IMPLEMENTED $12,090 $16,773 $6,105
90,562
kWh
$1,945
-
MMBtu
$4,040
-
gal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Liquid (haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs