Assessment Year | 1993 |
---|---|
Principal Product | Corrugated Cardboard |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 149 |
Plant Area |
199,633
ft2
|
Annual Production | 574,000
thousand feet
|
Production Hrs. Annual | 5,500
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $148,089 | 3,570,926 |
kWh
|
$0.041 |
Natural Gas | $166,298 | 52,082 |
MMBtu
|
$3.19 |
LPG | $6,535 | 1,472 |
MMBtu
|
$4.44 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $62,092 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $42,274 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $9,658 | $1,695 | - |
$9,658
-
MMBtu
|
- | |
02 | 2.2136: Install / repair insulation on steam lines | $8,592 | $13,864 | - |
$8,592
-
MMBtu
|
- | |
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $13,920 | $9,730 | - |
$13,920
-
MMBtu
|
- | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,718 | $704 | - |
$4,718
-
MMBtu
|
- | |
05 | 2.4133: Use most efficient type of electric motors | $4,026 | $12,064 |
$4,026
97,011
kWh
|
- | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,667 | $515 |
$1,667
40,152
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,198 | $10,312 |
$2,198
53,048
kWh
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,567 | $551 |
$1,567
37,808
kWh
|
- | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $646 | $301 |
$646
15,533
kWh
|
- | - | |
10 | 2.8113: Purchase gas directly from a contract gas supplier | $15,100 | $5,240 | - | - | $15,100 | |
TOTAL RECOMMENDED | $62,092 | $54,976 |
$10,104
243,552
kWh
|
$36,888
-
MMBtu
|
$15,100 | ||
TOTAL IMPLEMENTED | $42,274 | $49,032 |
$10,104
243,552
kWh
|
$32,170
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs