ITAC Assessment: SF0122
ITAC logo
ITAC Assessment: SF0122
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Tortillas & Tortilla Chips
NAICS
n/a
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 50
Plant Area 12,000
ft2
Annual Production 25,000,000
lb
Production Hrs. Annual 3,744
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $26,058 321,219
kWh
Electricity Demand $6,334 1,525
kW-mo/yr
Natural Gas $35,552 9,948
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $73,185 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,063

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.4133: Use most efficient type of electric motors $219 $376 $184
2,345
kWh
$35
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,448 $7,560 $2,084
25,791
kWh
$364
-
kW-mo/yr
- - -
03 2.2122: Install / repair insulation on condensate lines $196 $811 $196
16,120
kWh
- - - -
04 3.4151: Minimize water usage $1,544 $60 - - $1,544
-
Tgal
- -
05 3.4115: Recover and reuse cooling water $1,214 $765 $(-262.0)
(-3,224)
kWh
- $1,476
-
Tgal
- -
06 3.2111: Install redundant equipment to avoid losses caused by equipment failure and routine maintenance $9,844 $900 $(-78.0)
(-879)
kWh
- - $9,922
-
lb
-
07 3.2176: Increase use of automation $43,680 $47,000 - - - - $43,680
08 3.2176: Increase use of automation $13,000 $6,000 - - - - $13,000
09 4.423: Move product using mechanical means $1,040 $1,000 - - - - $1,040
TOTAL RECOMMENDED $73,185 $64,472 $2,124
40,153
kWh
$399
-
kW-mo/yr
$3,020
-
Tgal
$9,922
-
lb
$57,720
TOTAL IMPLEMENTED $10,063 $1,276 $106
1,466
kWh
$35
-
kW-mo/yr
- $9,922
-
lb
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs