Assessment Year | 1992 |
---|---|
Principal Product | TUBE FABRICATION |
NAICS |
n/a
|
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
n/a
|
Annual Production | 1,500
thousand feet
|
Production Hrs. Annual | 4,909
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $94,256 | 1,307,737 |
kWh
|
$0.072 |
LPG | $6,411 | 574 |
MMBtu
|
$11.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,636 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $192 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,284 | - |
$4,555
63,306
kWh
|
- | $(-271.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,034 | $1,600 |
$1,034
14,361
kWh
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $851 | $1,522 |
$851
11,723
kWh
|
- | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,364 | - |
$1,364
19,050
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,028 | $20 |
$3,028
41,911
kWh
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $746 | $438 |
$746
10,258
kWh
|
- | - | |
07 | 2.7492: Use proper thickness of insulation on building envelope | $192 | $620 | - |
$192
-
MMBtu
|
- | |
08 | 3.4115: Recover and reuse cooling water | $8,137 | $12,000 | - | - | $8,137 | |
TOTAL RECOMMENDED | $19,636 | $16,200 |
$11,578
160,609
kWh
|
$192
-
MMBtu
|
$7,866 | ||
TOTAL IMPLEMENTED | $192 | $620 | - |
$192
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs