ITAC Assessment: MO0054
ITAC logo
ITAC Assessment: MO0054
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product TUBE FABRICATION
NAICS
n/a
SIC 3498: Fabricated Pipe and Pipe Fittings
Sales Range $10
M
to 50
M
# of Employees 105
Plant Area
n/a
Annual Production 1,500
thousand feet
Production Hrs. Annual 4,909
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $94,256 1,307,737
kWh
LPG $6,411 574
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,636 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $192

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,284 - $4,555
63,306
kWh
- $(-271.0)
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,034 $1,600 $1,034
14,361
kWh
- -
03 2.4133: Use most efficient type of electric motors $851 $1,522 $851
11,723
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,364 - $1,364
19,050
kWh
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $3,028 $20 $3,028
41,911
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $746 $438 $746
10,258
kWh
- -
07 2.7492: Use proper thickness of insulation on building envelope $192 $620 - $192
-
MMBtu
-
08 3.4115: Recover and reuse cooling water $8,137 $12,000 - - $8,137
TOTAL RECOMMENDED $19,636 $16,200 $11,578
160,609
kWh
$192
-
MMBtu
$7,866
TOTAL IMPLEMENTED $192 $620 - $192
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs