Assessment Year | 1990 |
---|---|
Principal Product | RUBBER SEALS FOR WINDOWS |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 264 |
Plant Area |
n/a
|
Annual Production | 2,800,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $269,622 | 4,198,710 |
kWh
|
$0.064 |
LPG | $58,873 | 11,139 |
MMBtu
|
$5.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $61,654 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $55,351 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings |
---|---|---|---|---|---|---|
01 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $28,450 | $7,438 |
$28,450
443,142
kWh
|
- | |
02 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $7,357 | $464 | - |
$7,357
-
MMBtu
|
|
03 | 2.4221: Install compressor air intakes in coolest locations | $7,328 | $316 |
$7,328
114,302
kWh
|
- | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $5,637 | $2,693 |
$5,637
87,925
kWh
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,481 | $1,000 |
$4,481
69,754
kWh
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,890 | $1,226 |
$3,890
60,668
kWh
|
- | |
07 | 2.7444: Close holes and openings in building such as broken windows | $3,845 | $26 |
$3,845
59,789
kWh
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $666 | $106 |
$666
10,258
kWh
|
- | |
TOTAL RECOMMENDED | $61,654 | $13,269 |
$54,297
845,838
kWh
|
$7,357
-
MMBtu
|
||
TOTAL IMPLEMENTED | $55,351 | $10,470 |
$47,994
747,655
kWh
|
$7,357
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs