| Assessment Year | 2026 |
|---|---|
| Principal Product | Fabricated Structural and Architectural Metal |
| NAICS | 332312: Fabricated Structural Metal Manufacturing |
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $5 M to 10M |
| # of Employees | 30 |
| Plant Area |
16,000
ft2
|
| Annual Production | 1,000,000
lb
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Wyoming |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $13,480 | 210,312 |
kWh
|
$0.064 |
| Electricity Demand | $36,143 | 1,506 |
kW-mo/yr
|
$24.00 |
| Electricity Fees | $2,595 | - |
|
- |
| Natural Gas | $4,852 | 742 |
MMBtu
|
$6.54 |
| Fuel Oil #1 | $51,725 | 2,020 |
MMBtu
|
$25.61 |
| Fuel Oil #2 | $20,780 | 770 |
MMBtu
|
$26.99 |
| TOTAL YEARLY COSTS | $129,575 | |||
| RECOMMENDED SAVINGS* | $552,941 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.2176: Increase use of automation | $108,218 | $1,740,000 |
$(-2,640.0)
(-40,000)
kWh
|
$(-5,760.0)
-
kW-mo/yr
|
$116,618 | |
| 02 | 3.2176: Increase use of automation | $108,218 | $717,000 |
$(-2,640.0)
(-40,000)
kWh
|
$(-5,760.0)
-
kW-mo/yr
|
$116,618 | |
| 03 | 3.2176: Increase use of automation | $104,580 | $436,000 |
$(-132.0)
(-2,000)
kWh
|
$(-288.0)
-
kW-mo/yr
|
$105,000 | |
| 04 | 4.111: Add equipment/ operators to reduce production bottleneck | $117,621 | $572,000 |
$(-91.4)
(-1,385)
kWh
|
$1,094
-
kW-mo/yr
|
$116,618 | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,215 | $2,600 |
$2,215
33,550
kWh
|
- | - | |
| 06 | 4.112: Replace old machine with new automatic multi-station tool | $67,000 | $366,000 | - | - | $67,000 | |
| 07 | 2.4321: Upgrade obsolete equipment | $29,987 | $230,300 |
$259
3,920
kWh
|
$1,728
-
kW-mo/yr
|
$28,000 | |
| 08 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $15,103 | $291,632 |
$347
5,250
kWh
|
$2,016
-
kW-mo/yr
|
$12,740 | |
| TOTAL RECOMMENDED | $552,941 | $4,355,532 |
$(-2,683.2)
(-40,665)
kWh
|
$(-6,969.6)
-
kW-mo/yr
|
$562,594 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs