Assessment Year | 2021 |
---|---|
Principal Product | Aircraft Landing Gear |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
200,000
ft2
|
Annual Production | 30,000
pieces
|
Production Hrs. Annual | 6,552
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $447,939 | 6,869,323 |
kWh
|
$0.065 |
Electricity Demand | $183,414 | 15,687 |
kW-mo/yr
|
$11.69 |
Electricity Fees | $176,961 | - |
|
- |
Natural Gas | $19,200 | 5,000 |
MMBtu
|
$3.84 |
Fuel Oil #2 | $5,358 | 275 |
MMBtu
|
$19.48 |
TOTAL YEARLY COSTS | $832,872 | |||
RECOMMENDED SAVINGS* | $182,991 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $108,618 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3192: Use fossil fuel powered generator during peak demand periods | $48,176 | $80 | - | - | $48,176 | - | |
02 | 2.7221: Lower temperature during the winter season and vice-versa | $43,876 | $480 |
$35,107
540,115
kWh
|
$8,769
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,739 | $33,655 |
$16,134
248,221
kWh
|
$5,605
-
kW-mo/yr
|
- | - | |
04 | 2.3312: Install efficient rectifiers | $21,196 | $55,920 |
$15,841
243,703
kWh
|
$5,355
-
kW-mo/yr
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $19,025 | $120 |
$15,237
234,411
kWh
|
$3,788
-
kW-mo/yr
|
- | - | |
06 | 2.2511: Insulate bare equipment | $15,421 | $6,812 |
$12,299
189,216
kWh
|
$3,122
-
kW-mo/yr
|
- | - | |
07 | 2.6231: Utilize controls to operate equipment only when needed | $10,000 | $480 |
$6,761
104,011
kWh
|
$3,239
-
kW-mo/yr
|
- | - | |
08 | 2.4227: Use compressor air filters | $1,420 | $1,100 |
$1,420
21,847
kWh
|
- | - | - | |
09 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $1,362 | $616 |
$920
14,149
kWh
|
$257
-
kW-mo/yr
|
- |
$185
-
MMBtu
|
|
10 | 2.8112: Combine utility meters | $776 | $240 | - | - | $776 | - | |
TOTAL RECOMMENDED | $182,991 | $99,503 |
$103,719
1,595,673
kWh
|
$30,135
-
kW-mo/yr
|
$48,952 |
$185
-
MMBtu
|
||
TOTAL IMPLEMENTED | $108,618 | $91,891 |
$84,659
1,302,446
kWh
|
$23,774
-
kW-mo/yr
|
- |
$185
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs