Assessment Year | 1997 |
---|---|
Principal Product | Baked goods |
NAICS |
n/a
|
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $50 M to 100M |
# of Employees | 350 |
Plant Area |
120,000
ft2
|
Annual Production | 480,000,000
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $330,709 | 14,536,049 |
kWh
|
$0.023 |
Electricity Demand | $224,973 | 31,491 |
kW-mo/yr
|
$7.14 |
Electricity Fees | $3,314 | - |
|
- |
Natural Gas | $64,801 | 22,725 |
MMBtu
|
$2.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $957,886 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $860,636 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.1161: Eliminate/reduce an operation | $847,565 | $200,000 | - | - |
$847,565
-
lb
|
- | |
02 | 4.441: Install automatic packing equipment | $94,656 | $41,000 |
$(-114.0)
(-2,638)
kWh
|
- | - | $94,770 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,517 | $18,540 |
$4,135
140,094
kWh
|
$1,382
-
kW-mo/yr
|
- | - | |
04 | 3.5313: Increase amount of waste recovered for resale | $3,375 | - | - | - |
$3,375
-
lb
|
- | |
05 | 3.5313: Increase amount of waste recovered for resale | $2,414 | $8,400 |
$1,809
61,254
kWh
|
$605
-
kW-mo/yr
|
- | - | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $2,414 | $81 |
$1,809
61,254
kWh
|
$605
-
kW-mo/yr
|
- | - | |
07 | 2.2696: Use excess cold process fluid for industrial cooling needs | $1,608 | $14,500 |
$1,608
70,926
kWh
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $157 | $1,080 |
$118
4,103
kWh
|
$39
-
kW-mo/yr
|
- | - | |
09 | 3.1291: Eliminate practice of mixing waste streams | $180 | - | - | - |
$180
-
lb
|
- | |
TOTAL RECOMMENDED | $957,886 | $283,601 |
$9,365
334,993
kWh
|
$2,631
-
kW-mo/yr
|
$851,120
-
lb
|
$94,770 | ||
TOTAL IMPLEMENTED | $860,636 | $242,520 |
$7,670
276,377
kWh
|
$2,026
-
kW-mo/yr
|
$850,940
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs