Assessment Year | 2019 |
---|---|
Principal Product | Printing Ink |
NAICS | 334118: Computer Terminal and Other Computer Peripheral Equipment Manufacturing |
SIC | 3577: Computer Peripheral Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
130,000
ft2
|
Annual Production | 793
Tgal
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Puerto Rico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $994,746 | 5,962,683 |
kWh
|
$0.17 |
Electricity Demand | $114,122 | 13,636 |
kW-mo/yr
|
$8.37 |
Electricity Fees | $5,400 | - |
|
- |
TOTAL YEARLY COSTS | $1,114,268 | |||
RECOMMENDED SAVINGS* | $504,543 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $159,147 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $139,703 | $245,760 |
$130,706
782,670
kWh
|
$8,997
-
kW-mo/yr
|
|
02 | 2.6218: Turn off equipment when not in use | $103,161 | $14,000 |
$103,161
617,731
kWh
|
- | |
03 | 2.7425: Clean or color roof to reduce solar load | $91,845 | $61,708 |
$85,928
514,539
kWh
|
$5,917
-
kW-mo/yr
|
|
04 | 2.7221: Lower temperature during the winter season and vice-versa | $95,703 | $480 |
$89,594
536,493
kWh
|
$6,109
-
kW-mo/yr
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $31,941 | $59,135 |
$27,907
167,107
kWh
|
$4,034
-
kW-mo/yr
|
|
06 | 2.4226: Use / purchase optimum sized compressor | $20,441 | $72,870 |
$17,068
102,205
kWh
|
$3,373
-
kW-mo/yr
|
|
07 | 2.7229: Air condition only space necessary | $13,642 | $960 |
$12,763
76,428
kWh
|
$879
-
kW-mo/yr
|
|
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,503 | $2,020 |
$3,758
22,502
kWh
|
$745
-
kW-mo/yr
|
|
09 | 2.6127: Maintain air filters by cleaning or replacement | $3,604 | $2,070 |
$3,010
18,024
kWh
|
$594
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $504,543 | $459,003 |
$473,895
2,837,699
kWh
|
$30,648
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $159,147 | $148,075 |
$151,146
905,067
kWh
|
$8,001
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs