ITAC Assessment: MI0333
ITAC logo
ITAC Assessment: MI0333
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Surgical Products
NAICS 339112: Surgical and Medical Instrument Manufacturing
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 35,000
ft2
Annual Production 100,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $102,974 1,951,740
kWh
Electricity Demand $36,218 3,409
kW-mo/yr
Electricity Fees $25,377 -
Fuel Oil #2 $59,451 2,512
MMBtu
TOTAL YEARLY COSTS $224,020
RECOMMENDED SAVINGS* $351,865 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $47,602

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Administrative Changes Savings
01 4.231: Purchase equipment instead of leasing $304,263 $795,000 - - $59,451
-
MMBtu
$244,812
02 2.7229: Air condition only space necessary $17,320 $2,724 $13,177
248,614
kWh
$4,143
-
kW-mo/yr
- -
03 2.8114: Change rate schedules or other changes in utility service $10,427 $320 - - - $10,427
04 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system $7,399 $15,000 $5,806
109,557
kWh
$1,593
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $5,026 $13,843 $3,050
57,551
kWh
$1,976
-
kW-mo/yr
- -
06 2.3192: Use fossil fuel powered generator during peak demand periods $4,911 $80 - - - $4,911
07 2.2511: Insulate bare equipment $2,191 $2,240 $1,678
31,668
kWh
$513
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $328 $826 $328
6,185
kWh
- - -
TOTAL RECOMMENDED $351,865 $830,033 $24,039
453,575
kWh
$8,225
-
kW-mo/yr
$59,451
-
MMBtu
$260,150
TOTAL IMPLEMENTED $47,602 $35,033 $24,039
453,575
kWh
$8,225
-
kW-mo/yr
- $15,338
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs